Geomechanics, Streamlined.
© 2026 Geomechanics.io. All rights reserved.
50 articles tagged with Failure
Network Rail faces an estimated £9.05M repair bill after derailments at Lewes and Wickford, with restoration costs put at £5.4M and £3.65M respectively. The works will involve full track renewal in the affected possessions, ballast and formation reconstruction, and replacement of damaged signalling and overhead line equipment where required. The scale of expenditure signals significant disruption to asset condition budgets and may prompt closer scrutiny of inspection, maintenance and wheel–rail interface management on similar UK routes.
Residents of 14 properties evacuated after the partial collapse of three terraced houses in south London have been allowed back home more than 11 weeks after the incident. Structural engineers have evidently deemed the remaining buildings stable enough for reoccupation following inspections and temporary works to secure the damaged terrace. The case underlines the time and access constraints that follow even localised collapse events, with extended exclusion zones needed while assessing party wall integrity, shared foundations and potential progressive failure in dense urban streets.
Codelco has invested $32 billion over eight years while annual copper output has dropped from 1.7 Mt to 1.2 Mt, with an internal audit uncovering 42,100 t of inflated production that may trigger a $140 million adjustment. Chairman Bernardo Fontaine says the state miner’s costs are 78% above comparable operations and that structural governance failures, rising debt and declining grades mean it cannot develop its 1 million ha of concessions alone. He argues expanded joint ventures with partners such as Rio Tinto, BHP and Anglo American are essential to sustain roughly 1.3 Mt/y of production.
A blast at the Habas Demir Celik iron and steel plant in Aliaga, Izmir province, killed 16 workers when a ceiling crane snapped and fell into an arc furnace during molten steel casting around noon on 9 November. Ten people remain trapped under rubble, while 13 were injured and two are in serious condition, with casualties distributed across several regional hospitals. The Turkish government has opened an investigation, putting overhead crane integrity, furnace-area lifting operations and maintenance regimes under immediate scrutiny for heavy steel plants.
Northern Star Resources is working to stabilise the expanded KCGM processing plant in Western Australia after commissioning issues with mill motor control systems and associated equipment cut October output to 15,300oz from 766,000 tonnes of ore processed. The company is balancing this recovery effort with advancing its Hemi development in the Pilbara, maintaining project schedules while troubleshooting intermittent plant stoppages. For operators, the case underlines the production risk tied to complex drive and control upgrades on large grinding circuits during ramp-up.
Molson Group and subsidiary Molson Equipment Services have filed High Court notices of intention to appoint administrators after posting a £10.3m pre-tax loss on £333m turnover for the year to September 2024, despite operating 16 UK depots and employing around 600 staff with over 95 mobile service engineers. The Bristol-based heavy plant dealer distributes Kobelco excavators, Hyundai Construction Equipment, Thwaites dumpers, Sennebogen material handlers, Bell ADTs, Merlo telehandlers and Husqvarna demolition robots, making it a key supplier to plant hire, demolition and recycling contractors. Joint Administrators Ross Connock, Tom Crookham and Vesela Romagnoli have been appointed over Molson Equipment Services, Capital Equipment Finance, Aggregate Processing Solutions and Molson Scotland to manage their affairs and assets.
Codelco has halted processing at its Andina copper division after an obstruction in the tailings transport system near the Rápido RV4 sector caused a partial tailings release that may have entered the Blanco River within the Río Blanco canyon, upstream of the Aconcagua River basin. Emergency actions include shutting the concentrator, suspending tailings transport, diverting flows to the Piuquenitos reservoir, and continuous river sampling, while water utility Esval has closed its Aconcagua surface intake and switched to underground sources for Los Andes. The incident coincides with disclosure of 42,100 tonnes of previously inflated copper output and a 17,000‑tonne inventory reporting discrepancy, intensifying regulatory and community scrutiny of tailings and water-risk management at Andina.
Residents in north London report new cracking in Victorian brick terraces close to HS2 tunnelling works, prompting a local councillor to challenge HS2 Ltd over its handling of damage claims and communication. The concerns centre on potential ground movement and vibration from deep tunnel excavation beneath older, shallow‑founded masonry structures that often lack modern reinforcement or movement joints. For geotechnical and structural teams, the dispute raises scrutiny of settlement monitoring regimes, trigger levels, and the adequacy of pre‑condition surveys and compensation frameworks on urban tunnelling projects.
An out-of-service London Overground train struck the buffer stops at London Liverpool Street, derailing its first three carriages and sending the driver to hospital, according to an initial Rail Accident Investigation Branch update. The collision occurred on a terminal platform, with the impact severe enough to lift vehicles off the track and damage the buffer zone infrastructure. Investigators will focus on train speed on approach, buffer stop performance and any signalling or braking system issues, with implications for terminal platform risk assessments and buffer design margins on busy urban networks.
Endeavour Mining has suspended all underground production at the Mana gold mine in Burkina Faso after a section of the access ramp through the depleted Wona open pit subsided on 28 October, cutting access to the Dangouna and Aviera portals and triggering a full evacuation with no injuries. Ground-control specialists are assessing stability and portal remediation options, including a potential restart and acceleration via the remaining Wona portal and short-term reliance on nearby open-pit feed, with analysts estimating one to two quarters of disruption. Mana, which produced 173,000 oz. in 2025 and now contributes about 5–12% of Endeavour’s value and output, was already set to miss its 155,000–180,000 oz. guidance after earlier Siou underground depletion and delayed Bana Camp mining.
Two contractor employees from TJS Welding were killed in separate 3 Sept incidents at Kinross Gold’s Bald Mountain mine in Nevada, one struck by a failed truck-bed liner rigging and the other by a pipe that slipped off a jack, prompting mine-wide safety stand-downs while MSHA investigations continue. Kinross’ third-quarter attributable production fell 16% to 424,693 gold-equivalent ounces and all-in sustaining costs rose 20% to $1,947/oz, driving a 59% drop in attributable free cash flow to C$394.8 million despite a 23% higher realised gold price of $4,249/oz.
Alamos Gold has delayed commissioning of the Island Gold stage 3+ shaft to mid‑2027 and lifted its capex estimate about 5% above the original US$835 million budget after encountering a dyke in the underground ore and waste bin area that requires extra ground support and reinforcement of the loading pocket. Underground mining rates at Island Gold are still expected to exceed 2,000 t/d in H1 2027, rising to 2,400 t/d in H2, but slower development at Puerto Del Aire and seismic‑related rehabilitation at Young‑Davidson are set to weigh on 2027 production and costs. The Island Gold–Magino district expansion, including doubling Magino mill capacity to 20,000 t/d and targeting 534,000 oz/y at US$1,025/oz AISC from 2028, remains on schedule for Q1 2028 completion.
Strong-to-very strong El Niño conditions, with an 83% chance of exceeding all events since 1950, are set to disrupt copper and nickel supply through early 2027 via drought, flooding and power shortages across Latin America, Africa and Southeast Asia. Chilean and Peruvian copper hubs face flood risk to mines, smelters and ports—operations such as Los Bronces and El Teniente were previously halted in 2017—while Zambia and DRC copper smelters risk hydropower-driven load shedding. In Indonesia, drought has already forced output cuts at Morowali, with around 100,000 tonnes of NPI production affected.
Morton Salt has halted underground mining at its Fairport, Ohio rock salt operation after detecting a “significant inflow of water” on 22 October, triggering an immediate evacuation, shutdown of all underground activities and regulatory notifications. Surface work at the shaft complex is now “severely limited”, with the company declaring force majeure to customers and vendors while independent experts assess the source, extent and geotechnical implications of the water ingress. Local media report dozens of layoffs and say the future of mining at the site remains uncertain.
Two high-speed trains collided south of Madrid on 28 October, marking Spain’s second high-speed rail crash this year and prompting scrutiny of signalling and train control systems on one of Europe’s busiest AVE corridors. Investigators are focusing on a suspected computer malfunction within the traffic management or onboard control software, rather than track or civil works failure. For rail engineers, the incident raises immediate questions over redundancy in ETCS/ERTMS logic, fail-safe braking behaviour, and integration testing of software updates on high-speed lines.
Forty-two per cent of London Underground track is now rated in “very poor” condition, prompting the London Assembly’s Budget and Performance Committee to press Transport for London to accelerate capital renewals. A committee letter on “TfL capital renewals” warns of rising asset failures across deep tube tunnels, ageing points and crossings, and obsolete signalling equipment, with knock-on risks for speed restrictions and unplanned closures. TfL’s response centres on constrained funding in the current business plan and the need to prioritise life-expired track and civils on the oldest lines.
China Gold International Resources has restarted open-pit mining at the Chang Shan Hao (CSH) gold mine in Inner Mongolia after a 22 May slope instability halted operations for nearly five months, while keeping 2026 guidance at 70,732–83,592 oz of gold. Remediation followed geotechnical assessments and included haul road restoration, removal of loose rock, reinforcement of the landslide body, new drainage systems and continuous slope monitoring, enabling regulatory sign-off in late September. The processing plant ran throughout on low-grade stockpiles, and the mine will now blend fresh ore with stockpiled material to stabilise throughput and grades.
Three separate water main leaks occurred during Brighton and Hove City Council’s Western Road improvement scheme when construction works interacted with ageing buried pipework on the constrained urban corridor. BHCC’s cabinet member for transport explained that excavation and utility diversions around the live carriageway and footway triggered failures on existing mains rather than newly installed sections. The incidents forced short-term lane closures and emergency repairs, prompting closer coordination with the water undertaker on asset condition, trial holes and protection measures for remaining phases.
Boroo has agreed to acquire Victoria Gold for up to C$140 million to take over the Eagle gold mine in Yukon, where a June 2024 heap-leach failure caused about 1.8 million tonnes of material to escape containment. The Singapore-based group plans about C$800 million of spending from 2027–29 on rehabilitation, water treatment, heap stabilisation and a phased restart, with over C$600 million earmarked for sustaining and expansion over the initial mine life. A framework agreement with Yukon covers remediation, restart and closure, but court approval, allocation of legacy cleanup liabilities and Na-Cho Nyäk Dun engagement remain unresolved.
BHP chief executive Brandon Craig used his first AGM to reaffirm copper as the company’s primary growth engine, signalling further expansion at assets such as Escondida and Spence while keeping iron ore and metallurgical coal largely in a cash‑generation role. He conceded execution and cost‑control failures at the Jansen potash project in Saskatchewan, where capital costs have risen sharply since sanction, and framed future major projects around stricter stage‑gate approvals and contractor discipline. For engineers and project managers, this points to tighter cost benchmarks, more conservative schedules and closer scrutiny of brownfield debottlenecking options over large greenfield bets.
Anglian Water has been fined £1.6M after local mismanagement led to untreated sewage discharges into the River Brain in Essex over a six-week period in 2022, breaching its environmental permit. The Environment Agency investigation found operational failures at wastewater assets rather than storm-related exceedance, pointing to inadequate on-site oversight and response procedures. For civil and water engineers, the case signals closer regulatory scrutiny of network operations, incident logging and real-time monitoring on combined sewer overflows and treatment works.
Ofwat has proposed accepting a £280,000 enforcement package from Hafren Dyfrdwy after finding the company breached legal obligations in operating its wastewater treatment works and sewer network. The action follows failures in compliance at multiple assets, signalling closer scrutiny of treatment performance, discharge consents and network operation in the company’s largely rural Welsh service area. Designers and operators of wastewater infrastructure should expect tighter monitoring of process reliability, overflow management and asset condition, with potential implications for upgrade priorities and resilience planning.
Brighton & Hove City Council has refused to identify the contractors working on a road improvement scheme where a major Southern Water trunk main failed and took four days to repair. The leak occurred within an active highway works site, raising questions over coordination between the council’s term maintenance arrangements and Southern Water’s asset protection procedures. For civil and utilities engineers, the incident spotlights interface risk around large-diameter water mains in constrained urban corridors and the contractual opacity that can hinder lessons-learned and accountability.
Neso was forced to procure 1.2GW of power via the GB–France interconnector after a National Grid Electricity Transmission (NGET) asset overran its planned outage and failed to return to service on time. The unavailability of the transmission asset reduced domestic network capacity, triggering cross-border imports to maintain system stability and frequency control. For grid planners and civil engineers, the incident stresses outage scheduling discipline, contingency margins on key 400kV corridors, and the operational value of interconnector redundancy in constrained networks.
Final repairs have been completed on Godstone High Street, Surrey, 18 months after a major sinkhole caused a full closure and extensive ground stabilisation works. Engineers had to rebuild the carriageway and underlying formation, install new buried services and reinstate drainage after the collapse exposed significant voiding beneath the road. The incident is prompting local authorities and designers to review ground investigation scope, utility mapping and monitoring on similar chalk and solution-feature-prone corridors.
W G Carter Limited has been fined £120,000 plus £5,247 costs at Bristol Magistrates Court after 59-year-old worker Richard “Felix” Roper died falling from a stripped first floor onto a concrete ground slab at a barn house in Nether Westcote. A joint HSE and Gloucestershire Police investigation found work at height was not properly planned or supervised, with workers allowed onto joists where floorboards and structural supports had been removed while others continued lifting boards. After a Prohibition Notice, the firm switched to installing replacement joists from below using work-at-height equipment and blocking access to the first floor.
A passenger train in the 19 June 2024 Bedford collision accelerated from about 90mph to 98mph after its Automatic Warning System (AWS) demanded a brake application for a red signal, the Rail Accident Investigation Branch interim report finds. Data from the on-train recorder show the driver cancelled the AWS warning and power was reapplied roughly 600m before the signal protecting a set of facing points, after which the train struck a stationary engineering train. Investigators are examining driver behaviour, AWS/TPWS configuration on the route, and whether additional train protection or signalling controls could have prevented the overrun.
Brazil’s Grota do Cirilo lithium complex, Sigma Lithium’s only producing asset with 330,000 tonnes per year concentrate capacity, has halted all mining and processing after Minas Gerais regulator FEAM enforced a federal court order suspending environmental licences. The civil suit by Quilombola federation N’Golo centres on whether the Baú community, mapped 2.7 km from the operation within an 8-km consultation zone, was properly consulted, while Brazil’s National Mining Agency has separately ordered repairs to a damaged east wall in the north pit due to “imminent risk”. Sigma will rely on sales of lithium-bearing tailings, with no restart date and BMO cutting its 2027 output forecast from 278,000 to 207,000 tonnes.
South West Water has been fined £7.87M after a judge ruled that multiple environmental offences across Devon and Cornwall stemmed from “reckless failures” in its management systems and responses to known pollution risks. The case centres on repeated discharges from wastewater assets, with the court pointing to inadequate operational controls and risk management rather than isolated incidents. For civil and environmental engineers, the ruling signals closer scrutiny of sewerage network operation, monitoring regimes and contingency planning for combined sewer overflows and treatment works.
Above-ground risks have imposed or frozen more than $54 billion in Latin American mining since 2018, including a $31.7‑billion settlement for the 2015 Mariana tailings dam failure in Brazil and roughly $7 billion in stalled Peruvian copper projects plus $4 billion tied up in Mexico’s El Arco, San Nicolás and Cordero developments. AMI also cites Panama’s $6.8‑billion Cobre Panamá copper mine closure and over 700 days of transport-corridor blockades at Peru’s Las Bambas as emblematic of execution and social risk. Consultants report investors now heavily discount projects with uncertain permitting timelines, weak institutional legitimacy or high exposure to illegal mining.
A trackside fire reported and extinguished on Sunday 27 September near Clapham Junction has severely damaged signalling equipment, forcing an “extremely reduced train service” to and from London Victoria until at least 14:00 today. Network Rail signalling and permanent way teams worked overnight to reinstate key interlocking and lineside control circuits to keep a limited number of routes open through one of Europe’s busiest junctions. The incident exposes the vulnerability of legacy lineside signalling assets to localised fire and heat damage, with knock-on impacts on timetable resilience and maintenance planning.
Peninsula Energy’s Lance uranium project in northeast Wyoming has increased contained resources to 59 million lb. U3O8, including 15.5 million measured and indicated tonnes at 0.05% U3O8 and 38.5 million inferred tonnes at 0.04% U3O8, with the producing Ross area up nearly 16% to 7.4 million lb. Despite this, Peninsula has withdrawn its 2026 production guidance of 400,000–500,000 lb. U3O8 after low solution flow rates in ISR wellfields and has booked a US$50-million non-cash impairment on Units 1–3. The key technical risk now centres on whether the main Unit 4 at Ross can achieve design flow rates and head grades to support the maintained 2027 target of 500,000–600,000 lb. U3O8 and future development of the larger Kendrick and Barber areas.
St James Limited, developer of the Corniche residential towers beside Vauxhall Bridge, and window designer Lindner Prater have been fined after a penthouse window fell from height and killed a passer-by. The incident involved a large glazed unit detaching from the upper storeys of the high-rise façade, raising concerns over fixings, installation quality and inspection regimes on complex curtain wall and window systems. The case signals closer scrutiny of façade design responsibility, CDM compliance and maintenance procedures on tall residential schemes in dense urban locations.
A new draft supplemental environmental impact statement from the US Army Corps of Engineers and BLM models a 27% tailings storage facility failure at NOVAGOLD’s proposed Donlin Gold mine in Alaska, warning a toxic wave could reach Crooked Creek village in 90 minutes, bury it in tailings and leave metal contamination in the Kuskokwim River basin for more than a century. The scenario, far larger than the previously assessed 0.5% spill, projects long-term erosion, groundwater mounding, altered stream channels and persistent reductions in fish abundance, with NGOs demanding analysis of a full dam failure. The 40-million-ounce, 2.22 g/t deposit is permitted for 1.1 million ounces per year over 27 years, but the SEIS outcome could modify, reaffirm or rescind the existing federal permit.
Gemfields will book a $73.5 million half-year loss after a $125.2 million impairment at its Montepuez ruby mine in Mozambique, lifting the cumulative writedown on the asset to $65 million as premium ruby grades and recoveries lag expectations. The PP2 processing plant, designed to triple capacity from 200 to 600 tonnes per hour, has intermittently exceeded nameplate throughput but remains in final commissioning after transformer damage, excessive component wear, equipment defects and choking cut availability. Management has cut group operating costs by 17%, raised $30 million via a rights issue and sold Fabergé for $50 million as it focuses on stabilising Montepuez output and maintaining auction-driven cash flow.
Lithium-cesium-tantalum pegmatite projects are being advanced on simplified grade models that ignore strong mineralogical zoning, with cases such as Mount Marion showing fine-grained spodumene and high mica contents can destabilise DMS media, depress concentrate grades and force costly plant retrofits. At Canada’s Tanco pegmatite, assuming a uniform 60:40 spodumene–quartz intergrowth and overlooking iron and phosphate phases contributed to inefficient plant design and shutdowns. Patriot Battery Metals’ Shaakichiuwaanaan feasibility study similarly relies on a 1D Li₂O recovery formula, without 3D modelling of mica, arsenic and antimony domains that could flag low-density clay-rich zones and DMS underperformance.
Glencore has halted rail operations at its Cerrejón coal mine in Colombia after explosives hit its 150 km railway near Uribia, La Guajira, damaging a train in the sixth attack on the corridor this year. The mine itself, one of the world’s largest open pits with 2025 output of 16.8 million tonnes, continues operating while the National Army secures the line and engineers await access for damage assessment. Prolonged repairs could again choke inbound supplies and coal exports via Puerto Bolívar, exposing the operation’s heavy reliance on a single transport corridor.
Recurring failure of mining machine components is framed as a design signal rather than a pure maintenance issue, with repeated breakdowns driving higher planned and unplanned interventions and cutting equipment availability. MASPRO points to patterns such as identical wear on crusher liners or repeat cracking in the same boom or bucket locations as evidence that load paths, material selection or geometry need re-engineering, not just parts replacement. Reliability teams are urged to treat failure data as feedback for redesign, integrating field wear measurements and failure modes into upgraded component specifications.
Rail services between Watford Junction and London Euston were disrupted on 11 September by a lineside fire and a burst water main that flooded adjacent track, forcing service suspensions and diversions on the West Coast Main Line. Network Rail incident response teams were dispatched to extinguish the fire, inspect overhead line equipment and check for heat damage to ballast and sleepers, while separate crews worked to isolate the main and pump water clear of the formation. Engineers will need to assess subgrade softening, track geometry and signalling integrity before full line speed can be restored.
United Utilities has been fined £900,000 after admitting five environmental permit breaches linked to a major raw sewage discharge on the Fylde coast in June 2023, following failures in its wastewater treatment and overflow control systems. The incident involved untreated effluent bypassing normal screening and settlement processes during storm conditions, leading to prolonged discharge through combined sewer overflows into coastal waters used for bathing. For civil and environmental engineers, the case reinforces regulatory scrutiny on stormwater storage capacity, real-time CSO monitoring, and resilience of ageing sewer networks under intense rainfall events.
Surface reliability issues in drill rig breakout and rotation systems are being traced less to inadequate material hardness and more to surface engineering and load-path design, according to MASPRO’s field work on high-load components. MASPRO’s engineering team reports premature failures on rigs operating under continuous, shift-by-shift high torque and axial loads, where surface treatments and contact geometries, rather than bulk wear, govern life. For maintenance and design engineers, the findings point to closer scrutiny of surface finish, residual stress and lubrication regimes before simply specifying harder alloys.
Creditors have approved Company Voluntary Arrangements for seven firms in the Ardmore group, allowing an orderly wind-down of contracting operations rather than immediate liquidation. The group will exit construction contracting and concentrate on activities expected to generate higher recoveries for secured and unsecured creditors. Contractors, subcontractors and suppliers now face counterparty risk on existing Ardmore projects and should review payment exposure, retention sums and bond arrangements on live infrastructure and building contracts.
The UK’s 100 leading construction firms are showing incremental strengthening despite geopolitical instability and sustained inflation in materials and labour costs. Larger contractors are absorbing price pressures through scale and stronger balance sheets, while smaller subcontractors and specialist suppliers further down the supply chain are struggling to remain viable. The widening resilience gap raises execution risk on major infrastructure and building projects, with potential for subcontractor failures, programme delays and tighter prequalification and payment practices.
Homes on Benbuck View and Dunmoss View in Coalsnaughton, Clackmannanshire are to be demolished after Mining Remediation Authority investigations confirmed historic underground workings had caused active mine subsidence beneath the two streets. The decision follows visible ground movement reported on 18 May and subsequent detailed geotechnical assessments that ruled out practical stabilisation options for the affected plots. Engineers will now need to manage demolition, backfilling and long-term ground monitoring, with implications for foundations and service corridors on adjacent properties built over former coal measures.
A major fire at LondonEnergy’s Wembley Waste Transfer Station on Hannah Close, Neasden, has required 20 fire engines and about 125 firefighters to bring the blaze under control. The incident at the enclosed waste-handling facility raises immediate concerns over structural integrity of steel frames, cladding performance under high thermal loads, and potential damage to concrete slabs from prolonged heating and quenching. Engineers will need rapid assessment of fire spread pathways through waste stockpiles and building services to inform repairs, resilience upgrades and future fire-separation design.
The 14 August Greater Anglia derailment at Wickford, Essex occurred after the train driver reported a visible “kink” in the track, with on-board CCTV simultaneously capturing a clear lateral misalignment of the rail. The incident points to a localised geometry defect developing to the point of visible distortion between scheduled inspections, raising questions over the adequacy of current plain-line monitoring, patrol frequency and response times. For track engineers, the case will focus attention on integrating driver reports and CCTV evidence into real-time condition assessment and intervention protocols.
Lovell has paused construction on a nearby housing development in Charlton, south London, after three homes on Woodland Terrace suffered a partial collapse. Lovell took the decision to pause work while it works with the Royal Borough of Greenwich and other relevant parties to understand what happened. The cause of the incident has not been established. Lovell commissioned an independent structural engineer to carry out a visual survey of the properties.
Repair of the Bridgewater Canal breach at Little Bollington has advanced to contractor procurement after completion of survey and design work on the failed embankment. Engineers have now defined the repair scope, likely including reconstruction of the canal lining, reinstatement of the earthworks profile and improved seepage control to prevent repeat overtopping or piping. Contractors will need to manage works adjacent to live water infrastructure and local transport routes, with temporary cofferdams, dewatering and staged reinstatement expected to be key construction risks.
Highland Council will tell members that none of the three remediation options identified in a structural report for Balnaan Bridge can be funded, ruling out works to reopen it to vehicular traffic. The bridge, currently restricted to pedestrians and cyclists, would require substantial strengthening and deck works to restore road loading, but estimated costs exceed available capital budgets. Engineers and transport planners now face longer diversion routes for local traffic and potential reclassification of the structure if no interim load-limited solution is pursued.
A slope collapse at an open pit gold mine near Policarpa in Colombia’s Nariño department has killed 13 workers and injured seven, after a night-time landslide buried crews who were later recovered by firefighters and residents using excavators. Local authorities have not confirmed whether the operation had mining permits, despite witnesses saying around 50 people, mainly from the Quillacinga Indigenous group and including four victims from one family, regularly worked the site. The incident again exposes geotechnical and safety risks at Colombia’s largely unregulated artisanal and illegal gold mines, which involve an estimated 200,000–400,000 people.