Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    Failure
    Safety
    Projects

    Spey Viaduct collapsed spans: staged removal and investigation insights for engineers

    February 4, 2026|

    Reviewed by Tom Sullivan

    Spey Viaduct collapsed spans: staged removal and investigation insights for engineers

    First reported on New Civil Engineer

    30 Second Briefing

    Spey Viaduct’s collapsed spans over the River Spey will be cut and lifted out in sections under a Moray Council plan to create safe access for structural and geotechnical investigation following the 14 December failure. The segmented removal will allow close inspection of critical elements such as bearings, pier foundations and connection details that are currently submerged or unstable in the river channel. Findings are expected to inform both the viaduct’s future and any revisions to inspection and scour management regimes on similar river crossings.

    Technical Brief

    • Segmented removal will likely use mobile cranes and temporary lifting frames staged from both riverbanks.
    • Cut lines must be planned around existing welds, riveted joints and residual stress concentrations.
    • Access platforms and cofferdams may be required around piers to expose foundations and bearing seats safely.
    • Failure investigation will focus on scour depth, pier undermining, bearing condition and fatigue or corrosion at connections.
    • Continuous survey monitoring of remaining spans and piers is expected during cutting to detect any progressive movement.
    • CDM Regulations and temporary works design checks will govern lifting operations, exclusion zones and worker access routes.

    Our Take

    Within the 620 Infrastructure stories in our database, only a small subset of ‘Failure’ and ‘Safety’ items involve historic river crossings like Spey Viaduct, which tend to expose complex issues around scour, ageing foundations and inspection regimes rather than simple superstructure defects.

    The staged removal of the collapsed spans over the River Spey will likely be treated by Moray Council and their engineers as a rare full‑scale forensic opportunity, with lessons on hydraulic loading and residual capacity that can be fed back into management of other legacy steel and timber bridges in Scotland and the wider UK.

    Given how many ‘Projects’‑tagged failures in our coverage ultimately trigger revised design standards or new monitoring requirements, the December 14 collapse date is important: it falls in the high‑flow season for the Spey, which may strengthen the case for more conservative flood and debris‑impact allowances on similar river viaducts.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 10 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 9 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalMiningInfrastructureHazardsEnvironmentalSoftwarePolicy