    Green River Desimone levee failure: stability lessons for flood engineers

    December 15, 2025|

    Reviewed by Tom Sullivan

    Green River Desimone levee failure: stability lessons for flood engineers

    First reported on Geoengineer.org – News

    30 Second Briefing

    A levee breach on the Desimone levee along Washington’s Green River near Tukwila occurred under atmospheric river rainfall, with river levels peaking near 22 feet after a rapid 15‑foot rise in one week, exceeding six decades of recorded stages. The failure, a vehicle‑sized opening caused by internal erosion under prolonged high hydraulic loading, triggered flash flood warnings and evacuations for more than 45,000 residents in low‑lying areas. Emergency works using large sandbags and temporary fill stabilised the embankment, but saturated foundation soils and elevated groundwater leave wider regional levee and slope stability at risk from further storms.

    Technical Brief

    • Internal erosion risk was known pre-failure, with emergency seepage control measures already installed in the Desimone levee.
    • Breach geometry was highly localised, described as roughly the size of a passenger vehicle opening.
    • Emergency stabilisation used large sandbags and temporary fill placed by heavy equipment to buttress the eroded section.
    • Response actions were coordinated under flash-flood warning protocols, triggering formal evacuation notices in low-lying Green River communities.
    • Regional geotechnical risk increased by prior atmospheric river flooding, leaving foundation soils saturated and pore pressures elevated before this event.
    • Ongoing monitoring should prioritise piezometric levels, seepage emergence and slope deformation along adjacent levee reaches and valley slopes.
    • For ageing US levee systems, the case reinforces the need for continuous condition assessment and adaptive seepage-control upgrades under more frequent extreme storms.

    Our Take

    Among the 17 Hazards stories in our database, this Green River failure is one of the few that couples rapid river stage rise (15 ft in a week) with legacy levee systems, signalling that older urban flood defences in places like Tukwila, Kent and Renton are likely to be critical weak points during atmospheric river sequences.

    The 10‑year Sacramento River levee improvement horizon in the United States, contrasted with the relatively short 1 km new levee at Ormenio in Greece, suggests North American operators facing Green River–type events may need to prioritise staged upgrades and interim risk‑reduction measures rather than waiting for full corridor rebuilds.

    With fatalities highlighted in Shenzhen and Tahiti failures in the same Hazards category, the non‑fatal but disruptive Green River incident underscores that geotechnical teams in the Pacific Northwest should treat ground stability around levees as a safety issue on par with major slope and foundation collapses, not just a flood‑control problem.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    £100k fine for temporary works fail: critical lessons for site engineers
    Hazards
    1 day ago

    £100k fine for temporary works fail: critical lessons for site engineers

    A newly built breeze block retaining wall collapsed into a deep excavation on Old Coast Guard’s Road, Poole, crushing 69-year-old steel-fixer Patrick Grant and prompting a £100,000 fine for principal contractor Matrod Frampton Limited. HSE found the wall had been backfilled before the mortar had set, there was no temporary works design for the wall or other structures, and no temporary works co-ordinator or supervisor had been appointed despite a safety report warning eight days earlier. Rescue was further delayed by reliance on an unstable ladder and the absence of an excavation emergency plan.

    UK winter flooding: drainage design lessons for civil and geotechnical engineers
    Hazards
    3 days ago

    UK winter flooding: drainage design lessons for civil and geotechnical engineers

    Storms Amy and Benjamin have already flooded homes, closed key A-roads and rail links, and overwhelmed ageing culverts and combined sewers, exposing how far UK drainage and flood defences lag current rainfall intensities. Early-season events are overtopping river embankments and bypassing 1-in-100-year design standards in several catchments, forcing emergency pumping and temporary barriers in urban centres. For civil and geotechnical engineers, the message is tighter design margins, more storage and conveyance capacity, and accelerated retrofit of surface water systems before peak winter storms arrive.

    Builders fined £500 for asbestos failings: CDM compliance lessons for project teams
    Hazards
    6 days ago

    Builders fined £500 for asbestos failings: CDM compliance lessons for project teams

    A £500 fine has been imposed on McGrath Building & Joinery Contracts Ltd after HSENI found serious asbestos management failings during refurbishment of the Sacred Heart Chapel in Boho, Co. Fermanagh in November 2023. Investigators concluded the principal contractor did not adequately plan, manage or monitor works under Regulation 13(1) of the Construction (Design and Management) Regulations (Northern Ireland) 2016, particularly around identifying and safely removing licensed asbestos. The Enniskillen Magistrates’ Court conviction signals continued regulatory focus on CDM-compliant asbestos surveys and licensed removal on small refurbishment projects.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.