Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy
    Safety
    Failure
    Projects

    Hinkley Point C fire enforcement notices: safety lessons for project teams

    February 6, 2026|

    Reviewed by Joe Ashwell

    Hinkley Point C fire enforcement notices: safety lessons for project teams

    First reported on The Construction Index

    30 Second Briefing

    Fire enforcement notices have been served by the Office for Nuclear Regulation on all five MEH alliance contractors at Hinkley Point C – Altrad Babcock, Altrad Services, Balfour Beatty Kilpatrick, Cavendish Nuclear and NG Bailey – following a December 2025 inspection of the Unit 1 HF electrical building. Inspectors found no suitable fire risk assessment, inadequate means of escape with too few emergency exits for current workforce numbers, and combustible materials stored in a designated emergency stairway. The firms must now embed compliant fire arrangements, while main works contractors Bouygues Travaux Publics and Laing O’Rourke Delivery are separately facing court action over safety breaches.

    Technical Brief

    • Fire safety compliance was assessed against the Regulatory Reform (Fire Safety) Order 2005 within the Unit 1 HF building.
    • ONR’s targeted inspection in December 2025 focused specifically on MEH fire safety arrangements during installation phases.
    • Enforcement notices require not just corrective actions but embedding systematic fire arrangements to prevent recurrence across MEH activities.
    • ONR head of regulation explicitly framed fire safety as a non‑optional legal requirement directly protecting workforce life safety.

    Our Take

    Hinkley Point C is one of the few UK Infrastructure pieces in our database where the Office for Nuclear Regulation is named directly, which signals that fire protection non-compliances here are likely to trigger closer scrutiny of other high-hazard sites rather than being treated as routine construction issues.

    With five MEH alliance companies cited at the Unit 1 HF electrical building, this incident underlines the coordination risk in multi-contractor nuclear workscopes; practitioners on other UK megaprojects are likely to see ONR and client teams push harder for single-point accountability on life-safety systems during fit-out.

    Among the 652 Infrastructure stories and 1,800-plus safety- or failure-tagged items in our coverage, very few involve enforcement at the construction phase of a nuclear power station, so this case will probably become a reference example for UK fire strategy, temporary works, and permit-to-work regimes on complex energy builds.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 10 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 9 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.