    i-80 Gold’s US$500M Nevada plan: production, capex and risk notes for mine planners

    February 13, 2026|

    Reviewed by Joe Ashwell

    i-80 Gold’s US$500M Nevada plan: production, capex and risk notes for mine planners

    First reported on MINING.com

    30 Second Briefing

    i-80 Gold has secured a US$500 million package, including a US$250 million life-of-mine NSR royalty sale to Franco-Nevada (1.5%, rising to 3% from 2031) and a US$150 million gold prepay facility with National Bank and Macquarie plus a US$100 million accordion, to fund its Nevada growth plan and clear roughly US$175 million of debt. The financing is expected to fully fund Phase 1 and Phase 2, ramping Granite Creek, advancing Archimedes, and expanding Cove underground and the Granite Creek open pit to lift output from ~50,000 oz/year to 300,000–400,000 oz/year by 2031. Longer term, i-80 aims to develop the Mineral Point oxide heap leach project, which has 4.6 million oz Au-eq (measured and indicated) and a PEA outlining a 17-year life at 282,000 oz Au-eq/year, targeting total production of 600,000 oz/year across four Nevada operations.

    Technical Brief

    • Royalty deal grants Franco-Nevada a 1.5% NSR on all i-80 properties, doubling to 3% from 2031.
    • Of the US$250 million royalty, US$225 million is payable at closing targeted for March 2026.
    • Remaining US$25 million royalty tranche is earmarked for Mineral Point advancement post-early-stage permitting later in 2026.
    • Gold prepay with National Bank and Macquarie provides an initial US$150 million, plus a US$100 million accordion.

    Our Take

    With Mineral Point carrying 4.6 Moz Au-eq in measured and indicated resources over a 17-year mine life, i-80 Gold’s Nevada plan sits at the larger, longer-life end of the single-asset gold stories in our database, which may help justify the layered royalty and prepay structures with Franco-Nevada and the banks.

    The gold prepay facility capturing roughly 15% of output between 2028 and mid-2030 effectively front-loads cash flow from Granite Creek, Cove and Mineral Point, which is likely to constrain future hedging flexibility but materially de-risks build-out capex in Phase 1 to 2029.

    Extinguishing about $175 million of existing debt as part of this financing package positions i-80 Gold differently from other US gold developers like Liberty Gold at Black Pine (Idaho), which in our coverage are still largely in resource-growth mode rather than balance-sheet restructuring and multi-asset build-out.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 13 hours ago

    Mastermyne Tahmoor mine services award: contract structure and risks for engineers

    Mastermyne Group has secured a new mining services contract with GMT Mining Pty Ltd for the restart and ongoing operation of the Tahmoor underground coal mine in New South Wales. The mine was recently acquired by a consortium of M Group – Mastermyne’s largest shareholder – and Golden Energy and Resources (GEAR), and will be operated by GM3. The deal signals a structured restart pathway for Tahmoor, with clear separation between ownership (M Group/GEAR), operations (GM3) and contracted underground services (Mastermyne).

    Mining
    about 13 hours ago

    FLS Chile copper mine order: HPGR–ball mill flowsheet insights for process engineers

    FLSmidth has secured a major order in Chile to supply core grinding technologies for a new copper grinding line, including high-pressure grinding rolls (HPGR) and a ball mill. The package follows earlier collaborative engineering work on the mine’s expansion and is positioned as the next phase of a long-term process plant partnership with the unnamed customer. For process engineers, the HPGR–ball mill configuration signals continued confidence in energy-efficient comminution flowsheets for large-scale copper operations in the Andean region.

    Mining
    about 13 hours ago

    IMARC 2026: critical minerals, automation and electrification insights for engineers

    Australia’s Resources Minister Madeleine King is using IMARC 2026 in Sydney to position the country as a central hub in global critical minerals supply chains, with a strong focus on lithium, nickel and rare earths projects. The event is expected to draw thousands of delegates and several hundred exhibitors across exploration, mine automation and downstream processing, including OEMs showcasing autonomous haulage fleets and OEM-agnostic fleet management systems. For engineers, the agenda signals continued investment in electrified mobile equipment, high-throughput ore sorting and low-carbon refining technologies.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental