    Revival’s Utah Mercur gold mine: drilling, capex and schedule for project teams

    April 7, 2026|

    Reviewed by Tom Sullivan

    Revival’s Utah Mercur gold mine: drilling, capex and schedule for project teams

    First reported on MINING.com

    30 Second Briefing

    Revival Gold’s 2025 drilling at the past-producing Mercur gold project in Utah returned one of its strongest South Mercur intercepts to date, with hole RMC25-031 cutting 74 m at 2.8 g/t Au from 91 m downhole, including 13 m at 8 g/t from 13 m depth, and RMC25-032 intersecting 84 m at 1.1 g/t from 14 m. The company, which now owns 100% of Mercur after buying Barrick’s remaining stake, is advancing a heap leach operation based on a PEA outlining US$208 million capex for a 10-year, 95,000 oz/y mine. A 16,000 m follow-up drilling and engineering programme will feed into a pre-feasibility study targeted for Q1 2027, ahead of a potential construction decision in 2028 and first production in 2029.

    Technical Brief

    • Hole RMC25-172 at Mercur Hill intersected 23 m at 1.8 g/t Au from 102 m downhole.
    • Planned follow-up exploration and engineering drilling totals 16,000 m, restarting later this month.
    • Mercur property covers ~66 km², located 57 km from Salt Lake City with legacy mine infrastructure.
    • Historic operations by Barrick ran from mid‑1980s to 1997, shutting due to low gold prices, not depletion.
    • PEA‑stage heap leach restart at Mercur adds to Revival’s portfolio strategy targeting >160,000 oz/y total output.

    Our Take

    Our database shows multiple 2026 pieces on Revival Gold’s Mercur work, indicating the company is steadily advancing Utah ahead of its Beartrack-Arnett asset in Idaho; that sequencing suggests Mercur’s lower capex profile (about 208 million for a 10‑year life) is being used as the near-term platform to grow the Toronto-listed junior.

    Compared with recent Barrick Mining coverage focused on multi‑billion‑dollar copper‑gold builds like Reko Diq, Mercur’s envisioned heap‑leach restart in the western US sits at the opposite end of the capital spectrum, which likely makes it less exposed to the schedule and budget blowouts now affecting very large greenfield projects.

    The shallow oxide intercepts at Mercur and the 57 km distance to Salt Lake City, combined with the modest capex, put this gold project in a relatively favourable logistics and permitting context versus many other gold and copper projects in our 1,217‑story mining corpus, where remote access and infrastructure deficits are recurring constraints.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Ascension’s deep-underground critical minerals tech: process insights for mine planners
    Mining
    about 13 hours ago

    Ascension’s deep-underground critical minerals tech: process insights for mine planners

    Oxford University spinout Ascension has raised £1.7 million in new funding, combining a £670,490 Innovate UK Growth Catalyst grant with £1 million from UKI2S, Oxford Science Enterprises and East X, bringing total capital raised to £6.2 million. The company’s Selective Recovery programme targets rare earths and other critical minerals in deep volcanic glass, aiming to separate metals in situ and cut surface processing stages. Ascension’s process uses natural geothermal heat in volcanic rock deposits, avoiding excavation, high-temperature surface processing and associated land disturbance.

    Mining
    about 15 hours ago

    Holcim UK’s 20 LiuGong 870HE loaders: quarry power and layout implications for engineers

    Holcim UK is deploying 20 LiuGong 870HE pure electric wheel loaders across its quarry fleet, expanding one of the highest-tonnage battery-electric loader deployments in the sector. The 870HE units, among the largest pure electric loaders currently available, are targeted at high-duty quarry loading cycles traditionally dominated by diesel machines. For geotechnical and quarry operators, this signals accelerating adoption of heavy battery-electric equipment for primary load-and-haul, with implications for power supply design, charging infrastructure layout and ventilation requirements in future pit and plant planning.

    Gold price nears month high: planning implications for mine project teams
    Mining
    about 15 hours ago

    Gold price nears month high: planning implications for mine project teams

    Gold jumped 1.7% to about $4,887/oz, its highest level since 17 March, after Iran reopened the Strait of Hormuz, restoring commercial traffic through a corridor that carries roughly 20% of global oil flows. Silver climbed more than 5% to $83/oz, a five-week high, as easing energy-price and inflation fears revived expectations of interest rate cuts that favour non-yielding assets. Analysts at Zaner Metals and MKS PAMP see scope for a move back towards $5,000/oz in the near term, while Goldman Sachs keeps a bullish $5,400/oz year-end target.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.