    Montage moves up Côte d’Ivoire gold pour: capex, schedule and throughput notes for mine planners

    January 20, 2026|

    Reviewed by Joe Ashwell

    Montage moves up Côte d’Ivoire gold pour: capex, schedule and throughput notes for mine planners

    First reported on MINING.com

    30 Second Briefing

    Montage Gold has brought forward first gold pour at its Koné open-pit project in Côte d’Ivoire by six months to Q4 2026, with construction 63% committed on a US$545 million budget and targeting average production of about 301,000 oz. per year over the first eight years of a 16-year mine life. Key plant and infrastructure milestones include erection of all 14 carbon-in-leach tanks, delivery of the ball mill, completion of an oxide sizer, a new airstrip and a 33 kV camp power line, plus ongoing 225 kV substation and transmission tower works. A $16 million, 99,000-metre drilling programme in 2026, including work on the Wendé property and higher-grade satellites such as Petit Yao, aims to upgrade resources beyond the current 269 million indicated tonnes at 0.63 g/t (5.49 Moz) ahead of full ramp-up.

    Technical Brief

    • Koné licence covers 1,318 sq. km about 350 km northwest of Yamoussoukro, with multiple satellites.
    • More than 3,000 employees and contractors are currently on site supporting construction and early operations.
    • All 14 carbon-in-leach tanks plus associated piperack and grid-mesh walkways have been fully erected.
    • Oxide sizer installation is complete and the primary ball mill has been delivered to the plant site.
    • Permanent accommodation camp is almost finished, with all permanent rooms already fitted out and usable.
    • A new airstrip has been constructed and is scheduled to become operational within the current quarter.
    • Power infrastructure includes a near-complete 33 kV overhead line and an advancing 225 kV substation build.
    • Koné currently reports 269 Mt indicated at 0.63 g/t (5.49 Moz) and 43 Mt inferred at 0.51 g/t.
    • Resettlement village opened November, providing new housing plus school, pharmacy, maternity hospital, market and community facilities.

    Our Take

    Koné’s low indicated grade of 0.63 g/t gold, paired with a 16‑year mine life and a US$3.1‑billion after‑tax NPV, suggests Montage is engineering this as a large, low‑grade, bulk‑tonnage operation where power costs and plant uptime in Côte d’Ivoire will be critical to margins.

    With more than US$545 million already committed (63% of capex) and first gold pulled forward by six months, contractors and suppliers tied to the 225 kV power line and CIL plant at Koné are likely to see a tighter construction window and higher schedule risk than typical West African gold builds in our database.

    Among recent gold pieces in our coverage, Koné stands out for its scale relative to peers listing on the TSX/TSXV—such as Tiernan Gold or Goldsky Resources—implying Montage is positioning as a mid‑tier West Africa producer rather than an exploration-led junior.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    Cancel at any time.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 15 hours ago

    Worley at Bethune potash mine: compaction and power works explained for project teams

    Worley has secured a construction contract from K+S Potash Canada GP to deliver field construction services for the Compaction and Power Distribution project at the Bethune potash mine in Saskatchewan. The works form a core element of K+S’s long‑term Ramp-Up Program, aimed at increasing installed production capacity at the solution mine and associated processing plant. For contractors and suppliers, the award signals upcoming demand for compaction plant installation, power distribution upgrades and related brownfield integration in a live potash operation.

    Mining
    1 day ago

    Stone Three MPC and RTO in milling: control and sensing insights for plant engineers

    Stone Three is deploying industrial AI-enabled machine vision and smart sensors in South African and global concentrators to generate real-time measurements for comminution and flotation circuits that are traditionally hard to instrument. These data streams feed model predictive control (MPC) and real-time optimisation (RTO) layers, enabling tighter control of mill load, particle size distribution and flotation performance without adding new physical instrumentation. Remote process monitoring and diagnostics from Somerset West-based specialists support sites with limited on-site process control expertise, allowing continuous tuning of control models and faster response to changing ore conditions.

    Harbour Mining Survey on Chinese vs Western tech: key takeaways for mine planners
    Mining
    1 day ago

    Harbour Mining Survey on Chinese vs Western tech: key takeaways for mine planners

    A new Harbour Mining Survey of 100+ global mine operators and contractors compares confidence in Chinese versus Western mining technology and equipment, ahead of bauma CHINA 2026 in Shanghai. Respondents assess Chinese OEMs’ capabilities in battery-electric haul trucks, autonomous fleet systems and ultra-class hydraulic shovels against established Western suppliers such as Caterpillar, Komatsu and Sandvik. Findings point to faster adoption of Chinese equipment in surface coal and iron ore operations, with lingering concerns around software integration, lifecycle support and export‑market parts logistics.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental