    Montage moves up Côte d’Ivoire gold pour: capex, schedule and throughput notes for mine planners

    January 20, 2026|

    Reviewed by Joe Ashwell

    Montage moves up Côte d’Ivoire gold pour: capex, schedule and throughput notes for mine planners

    First reported on MINING.com

    30 Second Briefing

    Montage Gold has brought forward first gold pour at its Koné open-pit project in Côte d’Ivoire by six months to Q4 2026, with construction 63% committed on a US$545 million budget and targeting average production of about 301,000 oz. per year over the first eight years of a 16-year mine life. Key plant and infrastructure milestones include erection of all 14 carbon-in-leach tanks, delivery of the ball mill, completion of an oxide sizer, a new airstrip and a 33 kV camp power line, plus ongoing 225 kV substation and transmission tower works. A $16 million, 99,000-metre drilling programme in 2026, including work on the Wendé property and higher-grade satellites such as Petit Yao, aims to upgrade resources beyond the current 269 million indicated tonnes at 0.63 g/t (5.49 Moz) ahead of full ramp-up.

    Technical Brief

    • Koné licence covers 1,318 sq. km about 350 km northwest of Yamoussoukro, with multiple satellites.
    • More than 3,000 employees and contractors are currently on site supporting construction and early operations.
    • All 14 carbon-in-leach tanks plus associated piperack and grid-mesh walkways have been fully erected.
    • Oxide sizer installation is complete and the primary ball mill has been delivered to the plant site.
    • Permanent accommodation camp is almost finished, with all permanent rooms already fitted out and usable.
    • A new airstrip has been constructed and is scheduled to become operational within the current quarter.
    • Power infrastructure includes a near-complete 33 kV overhead line and an advancing 225 kV substation build.
    • Koné currently reports 269 Mt indicated at 0.63 g/t (5.49 Moz) and 43 Mt inferred at 0.51 g/t.
    • Resettlement village opened November, providing new housing plus school, pharmacy, maternity hospital, market and community facilities.

    Our Take

    Koné’s low indicated grade of 0.63 g/t gold, paired with a 16‑year mine life and a US$3.1‑billion after‑tax NPV, suggests Montage is engineering this as a large, low‑grade, bulk‑tonnage operation where power costs and plant uptime in Côte d’Ivoire will be critical to margins.

    With more than US$545 million already committed (63% of capex) and first gold pulled forward by six months, contractors and suppliers tied to the 225 kV power line and CIL plant at Koné are likely to see a tighter construction window and higher schedule risk than typical West African gold builds in our database.

    Among recent gold pieces in our coverage, Koné stands out for its scale relative to peers listing on the TSX/TSXV—such as Tiernan Gold or Goldsky Resources—implying Montage is positioning as a mid‑tier West Africa producer rather than an exploration-led junior.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Scope Systems cyber attack: resilience and risk lessons for mining IT teams
    Mining
    2 days ago

    Scope Systems cyber attack: resilience and risk lessons for mining IT teams

    A ransomware attack on Perth-based Scope Systems’ Pronto Xi ERP cloud stack disrupted dozens of mining customers, including Northern Star Resources and Evolution Mining, in what MM‑ISAC’s Rob Labbe calls the broadest single third‑party cyber event the sector has seen. Scope says client servers were restored from backups and not directly accessed, but admits internal data was exfiltrated and has not disclosed the attack vector, raising questions about visibility at hypervisor, storage and backup layers. The incident spotlights how multi‑tenant vCenter/ESXi environments, VM cloning and snapshot abuse—already used by groups like Akira—could expose integrated exploration, production and maintenance data across more than 400 Pronto Xi‑reliant mining operations.

    Newmont’s Red Chris underground expansion: block cave design and capex notes for engineers
    Mining
    2 days ago

    Newmont’s Red Chris underground expansion: block cave design and capex notes for engineers

    Newmont’s Red Chris mine in British Columbia has secured an amended Environmental Assessment Certificate and Mines Act permit, allowing a shift from open-pit to underground block caving and extending operations into the mid-2040s. The copper-gold porphyry deposit in the Golden Triangle hosts an estimated 20 million oz of gold and 13 billion lb of copper, with the block cave expected to lift Canada’s copper output by about 15%. The project entails several billion dollars in capital, around 1,800 construction jobs and roughly 1,500 operating roles at peak.

    Goldman cuts gold price forecast to US$4,900: planning notes for mine projects
    Mining
    2 days ago

    Goldman cuts gold price forecast to US$4,900: planning notes for mine projects

    Goldman Sachs has cut its end‑2026 gold price forecast by US$500/oz to US$4,900/oz after the US Federal Reserve, under new chair Kevin Warsh, signalled a hawkish shift that has pushed market-implied December rate hike odds to 87%. Spot gold has already fallen to about US$4,100/oz, down 27% from its near‑US$5,600/oz January peak, with three consecutive monthly losses between March and May and a 4% year‑to‑date decline. Goldman warns a 2026 year‑end target as low as US$4,400/oz is possible if rates rise, partly offset by ongoing central‑bank buying of roughly 50 tonnes/month this year and 40 tonnes/month next year.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy