    Coates–Brefni stormwater upgrade: temporary works lessons for road engineers

    November 27, 2025|

    Reviewed by Joe Ashwell

    Coates–Brefni stormwater upgrade: temporary works lessons for road engineers

    First reported on Roads & Infrastructure (AU)

    30 Second Briefing

    A stormwater upgrade on Cliff Drive in Leura, NSW’s Blue Mountains, replaced a failed culvert after landslip damage from repeated extreme rainfall, with civil contractor Brefni working on steep terrain and in environmentally sensitive bushland. Coates supplied an integrated shoring and dewatering solution plus plant hire, enabling safe excavation and culvert installation in unstable ground conditions while maintaining road access. The project was completed ahead of schedule and has since received an industry award, signalling the value of coordinated temporary works design in landslip-prone corridors.

    Technical Brief

    • For similar landslip-prone corridors, coordinated shoring–dewatering design is becoming standard risk control for culvert renewals.

    Our Take

    Within the 62 Infrastructure stories in our database, very few are tagged simultaneously as Projects, Safety and Failure, so the Cliff Drive works in Leura sit in a smaller subset that explicitly links construction delivery with learning from prior asset performance issues.

    NSW and the Blue Mountains feature in several safety-tagged infrastructure items in our coverage, suggesting local authorities are under sustained pressure to address legacy drainage and slope-stability vulnerabilities on constrained road corridors similar to Cliff Drive.

    For plant-hire and temporary works providers like Coates, being associated with an award-winning stormwater upgrade in Australia positions them well for future risk-averse councils that increasingly want contractors with a demonstrable track record on failure remediation rather than just lowest-cost supply.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy