    Vizsla’s Panuco project: security shock, cost and schedule risks for mine planners

    February 12, 2026|

    Reviewed by Tom Sullivan

    Vizsla’s Panuco project: security shock, cost and schedule risks for mine planners

    First reported on MINING.com

    30 Second Briefing

    Vizsla Silver is keeping its long-term development plans for the Panuco silver-gold project in Sinaloa after 10 workers were kidnapped on 23 January, at least five killed and five still missing, with site operations suspended but engineering work continuing remotely. Panuco hosts 12.8 million proven and probable tonnes grading 2.01 g/t gold and 249 g/t silver, with a planned 9.4‑year mine life producing 17.4 million silver‑equivalent oz. per year at an AISC of $10.61/oz and over 20 million oz. annually in the first five years. National Bank Financial now expects first production to slip from 2027 to around 2030 and warns security, labour and inflation could add up to $5/t to costs, as more than 1,000 Mexican troops and elite marines remain deployed in the district.

    Technical Brief

    • Kidnapped workers were intercepted on a 15 km commute corridor between Concordia camp and mine.
    • Ten employees were abducted on 23 January, including engineers and technical personnel supporting operations.
    • At least five victims have been formally identified from 10 bodies recovered in a clandestine grave.
    • More than 1,000 Mexican troops, including elite marines, are deployed in Sinaloa for search and protection.
    • Site activities are suspended, with mine planning and engineering work shifted to remote execution workflows.

    Our Take

    With an all-in sustaining cost of US$10.61/oz silver-equivalent at Panuco, Vizsla Silver sits in the lower-cost band of primary silver developers in our database, which gives the project more headroom to absorb security-driven operating cost increases such as the indicated potential US$5/t rise.

    The projected 17.4Moz silver-equivalent per year over a 9.4-year mine life, with more than 20Moz/a in the first five years, would place Panuco among the larger single-asset silver producers in our recent Latin America coverage, meaning prolonged security instability in Sinaloa could have an outsized impact on regional silver supply scenarios.

    Among safety-tagged Latin American underground mine items in our database, very few involve incidents on the scale of 10 kidnapped workers and multiple fatalities, suggesting that security risk at Panuco is now likely to be a primary factor in lender and insurer due diligence rather than a secondary ESG consideration.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Global battery demand and Australian lithium: processing shift for mine engineers
    Mining
    42 minutes ago

    Global battery demand and Australian lithium: processing shift for mine engineers

    Surging global demand for lithium-ion batteries for electric vehicles and grid storage is pushing Australia to move beyond spodumene concentrate exports into domestic refining and cathode‑grade chemical production. Industry proposals centre on converting hard‑rock feed into battery‑grade lithium hydroxide and carbonate in Western Australia, leveraging existing Tier‑1 deposits and port infrastructure but facing high energy costs, skills shortages and permitting timelines. For miners and process engineers, the shift implies greater focus on impurity control, reagent optimisation and integration of hydrometallurgical circuits with upstream mine planning.

    Bengalla growth for New Hope: strip mine sequencing and design notes for planners
    Mining
    about 1 hour ago

    Bengalla growth for New Hope: strip mine sequencing and design notes for planners

    New Hope Group has lifted coal output across its Australian assets and is advancing growth plans at the Bengalla thermal coal mine in the Hunter Valley, where it holds an 80 per cent interest alongside Mitsui, Taipower and J-Power. The open-cut operation, which typically produces export-quality thermal coal for Asian power utilities via the Port of Newcastle, is the company’s key near-term expansion focus. For mine planners and geotechs, any Bengalla growth path will centre on additional strip mining, dragline and truck–shovel sequencing, and associated waste dump and haul road reconfiguration.

    Mining smarter with AI and data: edge network design notes for engineers
    Mining
    about 2 hours ago

    Mining smarter with AI and data: edge network design notes for engineers

    Australian miners are hitting a data wall as high‑bandwidth sensors, autonomous fleets and video streams overwhelm traditional cloud links, pushing operations towards private LTE networks and on‑site edge computing. Vendors such as Vocus are pairing Starlink Business Rural satellite backhaul with 4G/5G private LTE to keep haul trucks, crushers and fixed plant connected in real time, even on remote pits and waste dumps. For engineers, this shift means designing networks and control systems around low‑latency, on‑site processing for fleet dispatch, collision avoidance and condition monitoring rather than centralised data centres.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.