    Sierra Madre buys Del Toro silver mine: restart schedule and capex notes for engineers

    December 18, 2025|

    Reviewed by Joe Ashwell

    Sierra Madre buys Del Toro silver mine: restart schedule and capex notes for engineers

    First reported on MINING.com

    30 Second Briefing

    Sierra Madre Gold & Silver is acquiring First Majestic’s 100%-owned Del Toro silver mine in Zacatecas for up to $60 million, with $30 million due at closing (US$20 million cash, US$10 million in shares) and two further US$10 million milestone payments tied to a >100 million oz AgEq resource and achieving commercial production within five years. Del Toro comprises three fully permitted underground mines, a 3,000 t/d flotation plant and 62.5 km of existing development over 21.6 sq. km of concessions, with historic resources of 7.57 million oz AgEq (M&I) and 11.18 million oz (inferred). Sierra Madre plans ~50,000 m of drilling, an updated resource by early 2028, and a staged restart from mid-2027, while keeping open an accelerated restart within 12 months if silver prices stay strong.

    Technical Brief

    • Del Toro’s processing plant is a 3,000 t/d flotation circuit, already built and fully permitted.
    • Underground infrastructure includes over 62.5 km of existing development across three permitted mines.
    • Historic production averaged 2.54 million oz AgEq per year between 2015 and 2018 before shutdown.
    • Operations were placed on care and maintenance in January 2020 to improve portfolio cash flow margins.
    • Del Toro was originally commissioned by First Majestic in 2013 as its fifth producing silver mine.
    • Sierra Madre must complete a C$40 million private placement at C$1.30/share as a closing condition.

    Our Take

    The staged US$60 million structure and C$40 million private placement mean Del Toro will compete directly with La Guitarra and the San Jorge copper-gold project for Sierra Madre’s capital, effectively prioritising near-term silver ounces in Mexico over advancing its Argentine copper-gold exposure.

    Historic resources of 7.57 million oz measured and indicated plus 11.18 million oz inferred at Del Toro versus a 100 million oz silver-equivalent trigger for the contingent payment signal that Sierra Madre is betting on substantial exploration upside or reclassification of mineralisation rather than simply restarting on the existing resource base.

    With three fully permitted underground mines and 62.5 km of development already in place at Del Toro, Sierra Madre’s indicated 12‑month ‘fast-track’ restart option is unusually short compared with most silver entries in our database, suggesting the main gating items will be financing and silver price levels rather than permitting or new infrastructure.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 16 hours ago

    Tapojärvi at Sotkamo Silver mine: continuity and risk notes for production engineers

    Tapojärvi has restarted as main mining contractor at Sotkamo Silver’s underground silver mine in Finland, resuming a role it previously held from 2018 to 2023 under a new agreement signed in June 2025. The contract covers full-scale production mining services, including drilling, blasting, loading and haulage in a familiar orebody and infrastructure, allowing rapid ramp-up using existing site knowledge and established operating procedures. For geotechnical and production engineers, continuity in contractor, ground control methods and equipment fleet should reduce interface risk and support stable output planning.

    STRACON’s Los Bronces tailings dam contract: lifecycle model insights for engineers
    Mining
    about 23 hours ago

    STRACON’s Los Bronces tailings dam contract: lifecycle model insights for engineers

    STRACON has secured an integrated engineering, construction, financing and long-term operations and maintenance contract for the Pérez Caldera Tailings Dam at Anglo American Sur’s Los Bronces copper operation in Chile’s Lo Barnechea district. The scope combines dam design and build with funding and multi-year O&M, signalling a bundled delivery model for critical tailings infrastructure rather than separate EPC and operator contracts. For geotechnical and tailings engineers, this points to growing demand for contractors capable of lifecycle stewardship under Chile’s stringent post-Brumadinho regulatory environment.

    Metso’s third orders for Almalyk copper smelter: design and ramp-up notes for engineers
    Mining
    2 days ago

    Metso’s third orders for Almalyk copper smelter: design and ramp-up notes for engineers

    Metso has booked the third tranche of orders for JSC Almalyk Mining and Metallurgical Complex’s copper smelter project in Uzbekistan, following equipment and project services contracts announced on 9 August 2024. The first two tranches, totalling €146 million, were booked in Q4 2024, with the latest booking covering additional core process equipment and associated services for the greenfield smelter complex. The staged order intake signals a multi-phase build-out where process design, commissioning support and long-lead items will be critical for throughput, energy performance and sulphur capture compliance.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.