Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    Projects
    Contract Award

    Second HPC reactor arrives: schedule, constructability and logistics lens

    January 13, 2026|

    Reviewed by Tom Sullivan

    Second HPC reactor arrives: schedule, constructability and logistics lens

    First reported on The Construction Index

    30 Second Briefing

    Delivery of Hinkley Point C’s second reactor pressure vessel marks a key milestone for Unit 2, with the 500‑tonne, 13‑metre‑long high‑strength steel cylinder shipped from Framatome’s Saint Marcel plant via Avonmouth and Combwich Wharf before a six‑hour, four‑mile heavy road move to site. Unit 1’s vessel, installed and welded in 2023, is now followed by intensive fit‑out of pipes, cables and equipment, while Unit 2 work centres on building completion after last July’s dome lift. EDF now expects Unit 1 to start generating in 2029–30, with Unit 2 a couple of years later, aided by 25% faster construction and about 60% prefabrication.

    Technical Brief

    • Reactor pressure vessel is a 500‑tonne, 13‑metre‑long high‑strength steel cylinder for Unit 2.
    • Component was fabricated at Framatome’s Saint Marcel factory in France before UK transport logistics.
    • Sea leg used Avonmouth Docks to Combwich Wharf barge transfer on the River Parrett.
    • Final heavy haul was a six‑hour, four‑mile move by specialised multi-axle transporter.
    • Unit 1’s identical vessel is already installed and fully welded in place on Unit 1 of the power station.
    • Original Unit 1 generation date slipped from 2025 to 2027, now expected to be operation in 2029–30.
    • Unit 2 completion is now planned roughly “a couple of years” after Unit 1’s operation date.
    • Construction teams report Unit 2 build about 25% more quickly than Unit 1, with prefabrication now approaching 60%.

    Our Take

    The 25% faster build rate and roughly 60% prefabrication on Hinkley Point C Unit 2 signal that UK nuclear delivery is starting to capture learning-curve efficiencies, which will be closely watched as a benchmark for Sizewell C and any future EPR deployments.

    Moving 500‑tonne, 13 m reactor pressure vessels via Avonmouth Docks and Combwich Wharf underlines how critical specialist port and heavy‑haul logistics are for large UK infrastructure; in our database, only a handful of Infrastructure pieces involve comparable abnormal load constraints.

    The slip from the original 2025 generation target for Unit 1 to a 2027 reset, with talk of 2029–2030, puts schedule pressure on UK decarbonisation planning, likely increasing the system value of life‑extension and grid‑scale storage projects that appear elsewhere in recent Infrastructure coverage.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers
    Infrastructure
    about 1 month ago

    Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers

    Strabag and Group company Züblin have secured the design-and-build structural works for the ABS Gäubahn Nord/Pfaffensteig Tunnel in south-west Germany, centred on an 11km twin-bore rail tunnel linking Stuttgart Airport station directly to the Gäubahn line towards Switzerland. About 9.8km will be driven by two TBMs, with conventional tunnelling for the A8 motorway undercrossing and airport connection, plus a 240m cut-and-cover section, retaining structures, railway underpasses and a grade-separated crossing. A 3km surface section will be upgraded and partially realigned for 200km/h operation, delivered under an integrated project delivery model with Ed. Züblin, Wayss & Freytag and Strabag AG sharing tunnelling, structural and earthworks packages.

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers
    Infrastructure
    3 months ago

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers

    A 271.5‑tonne Herrenknecht Mixshield TBM, Caroline, has started driving a 2.2km electricity cable tunnel with a 4m internal diameter beneath the River Thames in Essex for National Grid’s Grain to Tilbury project, delivered by the Ferrovial BEMO joint venture. The drive will pass through variable Thames estuary ground conditions between 35m‑deep launch and reception shafts of 15m and 12m diameter, with tunnelling continuing into 2026 and overall scheme completion targeted for 2029. The new tunnel will replace the 1969 Thames Cable Tunnel and carry new high‑voltage circuits between Grain and Tilbury substations.

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    4 months ago

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy