Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy
    Projects
    Contract Award

    Second HPC reactor arrives: schedule, constructability and logistics lens

    January 13, 2026|

    Reviewed by Tom Sullivan

    Second HPC reactor arrives: schedule, constructability and logistics lens

    First reported on The Construction Index

    30 Second Briefing

    Delivery of Hinkley Point C’s second reactor pressure vessel marks a key milestone for Unit 2, with the 500‑tonne, 13‑metre‑long high‑strength steel cylinder shipped from Framatome’s Saint Marcel plant via Avonmouth and Combwich Wharf before a six‑hour, four‑mile heavy road move to site. Unit 1’s vessel, installed and welded in 2023, is now followed by intensive fit‑out of pipes, cables and equipment, while Unit 2 work centres on building completion after last July’s dome lift. EDF now expects Unit 1 to start generating in 2029–30, with Unit 2 a couple of years later, aided by 25% faster construction and about 60% prefabrication.

    Technical Brief

    • Reactor pressure vessel is a 500‑tonne, 13‑metre‑long high‑strength steel cylinder for Unit 2.
    • Component was fabricated at Framatome’s Saint Marcel factory in France before UK transport logistics.
    • Sea leg used Avonmouth Docks to Combwich Wharf barge transfer on the River Parrett.
    • Final heavy haul was a six‑hour, four‑mile move by specialised multi-axle transporter.
    • Unit 1’s identical vessel is already installed and fully welded in place on Unit 1 of the power station.
    • Original Unit 1 generation date slipped from 2025 to 2027, now expected to be operation in 2029–30.
    • Unit 2 completion is now planned roughly “a couple of years” after Unit 1’s operation date.
    • Construction teams report Unit 2 build about 25% more quickly than Unit 1, with prefabrication now approaching 60%.

    Our Take

    The 25% faster build rate and roughly 60% prefabrication on Hinkley Point C Unit 2 signal that UK nuclear delivery is starting to capture learning-curve efficiencies, which will be closely watched as a benchmark for Sizewell C and any future EPR deployments.

    Moving 500‑tonne, 13 m reactor pressure vessels via Avonmouth Docks and Combwich Wharf underlines how critical specialist port and heavy‑haul logistics are for large UK infrastructure; in our database, only a handful of Infrastructure pieces involve comparable abnormal load constraints.

    The slip from the original 2025 generation target for Unit 1 to a 2027 reset, with talk of 2029–2030, puts schedule pressure on UK decarbonisation planning, likely increasing the system value of life‑extension and grid‑scale storage projects that appear elsewhere in recent Infrastructure coverage.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 7 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Xihe on Tung Chung Line down-track: TBM turnback method and risks for tunnel engineers
    Infrastructure
    in 5 months

    Xihe on Tung Chung Line down-track: TBM turnback method and risks for tunnel engineers

    TBM Xihe, a 7.3m-diameter, 100m-long, 1,000-tonne Herrenknecht slurry machine, has completed the up-track drive to the future Tung Chung West Station and has begun boring the down-track tunnel towards Tung Chung Station for MTR’s Tung Chung Line Extension in Hong Kong. The Bouygues Travaux Publics–Dragages Hong Kong JV turned the TBM underground within the launch shaft using a push-pull method and self-propelled modular transporter, avoiding full disassembly and surface transport. About 1.3km of new twin-bore tunnels are being driven close to existing rail and urban structures, with commissioning targeted for 2029.

    Sydney Metro Stations Package West: design and delivery notes for engineers
    Infrastructure
    in 4 months

    Sydney Metro Stations Package West: design and delivery notes for engineers

    Gamuda Engineering has secured the Sydney Metro Stations Package West as principal contractor, covering design and construction of five new underground stations at Westmead, North Strathfield, Burwood North, Five Dock and The Bays on the 24km Sydney Metro West line between Greater Parramatta and the CBD. The scope includes deep station boxes, entrances and access points, full station fit-out and integration with surrounding precincts, with Laing O’Rourke and DT Infrastructure joining as MetroVista delivery partners. Site works are scheduled to start on Monday, 5 January 2026.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.