Geomechanics.io

  • Free Tools
Sign UpLog In
AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    Projects
    Contract Award

    Octavius £112m Walsgrave junction upgrade: design and phasing notes for engineers

    February 5, 2026|

    Reviewed by Joe Ashwell

    Octavius £112m Walsgrave junction upgrade: design and phasing notes for engineers

    First reported on The Construction Index

    30 Second Briefing

    Planning consent via a development consent order has been granted for the A46 Walsgrave junction upgrade on Coventry’s outskirts, a scheme previously costed at £112m and classed as a nationally significant infrastructure project on the Trans-Midlands Trade Corridor between the M5 and Humber ports. The project will replace the existing three-arm priority roundabout linking the A46 and B4082 with a free-flowing A46 mainline while maintaining local access, targeting reduced delays for around 57,000 daily users. National Highways and main contractor Octavius Infrastructure will now finalise design and updated costs, with construction due to start in autumn 2026 and opening in 2028.

    Technical Brief

    • Development Consent Order under the Planning Act 2008 classifies the junction as a Nationally Significant Infrastructure Project.
    • Existing junction form is a three-arm priority roundabout connecting the A46 trunk road with the B4082.
    • Upgrade design introduces a free-flow mainline A46 with separate local access movements retained.
    • National Highways is client; Octavius Infrastructure appointed as main contractor for detailed design and delivery.
    • Previous capex estimate of £112m is now being rebaselined, implying cost risk from inflation and scope refinement.
    • Scheme sits on the Trans‑Midlands Trade Corridor between the M5 and Humber Ports, prioritising freight reliability.
    • Daily demand of around 57,000 vehicles drives capacity, queuing and safety performance requirements for the new layout.

    Our Take

    Within our 636-item Infrastructure corpus, there are relatively few pieces focused on Coventry and the midlands road network, so the A46 Walsgrave junction upgrade stands out as one of the more substantial regional highway schemes scheduled into the late-2020s pipeline.

    The 2021 and 2025 ownership changes for Octavius Infrastructure, culminating in acquisition by the RSK consultancy group, suggest this £112m-class highways job will be delivered under a more integrated contractor–consultant model than many legacy National Highways schemes in our database.

    With construction not expected to start until autumn 2026 and opening targeted for 2028, the A46 scheme will overlap with other midlands and southwest corridor works in our coverage, which is likely to tighten demand for specialist traffic management, ground investigation and structures resource along the Trans-Midlands Trade Corridor.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.