Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy
    Projects
    Sustainability

    Lower Thames Crossing low carbon steel: supply and design notes for project teams

    February 19, 2026|

    Reviewed by Joe Ashwell

    Lower Thames Crossing low carbon steel: supply and design notes for project teams

    First reported on New Civil Engineer

    30 Second Briefing

    British suppliers could provide 85–90% of the Lower Thames Crossing’s low carbon steel demand, based on recent market engagement by the project team. The scheme, which includes a new Thames tunnel and major approach viaducts carrying the A122 and M25, is expected to require large volumes of structural and reinforcement steel with reduced embodied carbon relative to conventional UK steel. For designers and contractors, this signals strong potential to specify UK-sourced low carbon sections and rebar, simplifying assurance on supply chains and whole-life carbon targets.

    Technical Brief

    • Findings give designers early confidence to embed low-carbon steel assumptions into outline and detailed design stages.
    • Procurement teams gain evidence to structure tenders favouring verified low-carbon UK mills and fabricators.
    • Supply-chain assurance is simplified by concentrating traceability, EPD data and certification within a predominantly domestic network.
    • For contractors, shorter steel logistics chains reduce programme risk from port congestion and international freight disruption.
    • Results provide a template for similar UK megaprojects to pre-test local low-carbon material capacity.

    Our Take

    Within the 741 Infrastructure stories in our database, steel appears far less frequently than concrete in decarbonisation discussions, so using low‑carbon steel at the Lower Thames Crossing signals a shift in where embodied‑carbon savings are being sought.

    The ability for British suppliers to cover roughly 85–90% of low‑carbon steel demand on a single flagship project suggests domestic mills and fabricators are already scaling green steel offerings, which could tighten specification standards for future UK infrastructure tenders.

    Given that this sits in the Sustainability‑tagged subset of our coverage, contractors on other major UK projects using steel are likely to face pressure to demonstrate similar domestic low‑carbon sourcing options in order to remain competitive at bid stage.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.