    Kinross $1.5B Lobo-Marte gold project: design, capex and schedule notes for engineers

    April 1, 2026|

    Reviewed by Tom Sullivan

    Kinross $1.5B Lobo-Marte gold project: design, capex and schedule notes for engineers

    First reported on MINING.com

    30 Second Briefing

    Kinross Gold has lodged its $1.5 billion Lobo-Marte project with Chile’s Environmental Impact Assessment System, proposing sequential open-pit mining of the Marte and Lobo deposits in the Atacama region over a 16-year life. The plan centres on a static, six-phase heap leach pad and plant processing about 35,000 tonnes per day, supplied by freshwater piped from existing Mantos de Oro wells near Nevado Tres Cruces National Park and power from a 220 kV line. A 3.5-year build is envisaged, with production of roughly 4.7 million oz at an AISC of $680/oz, starting after La Coipa closes 50 km away.

    Technical Brief

    • Static heap leach pad is planned to grow through six discrete expansion phases over the mine life.
    • Fresh water will be piped from existing Mantos de Oro wells within the Nevado Tres Cruces exclusion zone.
    • Power supply is to be secured via a dedicated 220 kV transmission line connection.
    • Environmental Impact Assessment submission to SEIA formally initiates Chile’s multi-stage environmental and social permitting process.
    • November 2021 feasibility study embeds environmental and community constraints directly into mine and plant layout.
    • Chile’s mining minister explicitly links project viability to a “robust” but non-obstructive permitting and regulatory framework.
    • Lobo-Marte joins recent large-scale Chilean permit applications by BHP, Freeport-McMoRan and Albemarle, signalling a clustered project pipeline.

    Our Take

    Kinross Gold’s push on Lobo-Marte in Chile sits alongside its C$1.4 billion Great Bear project in Ontario, which our coverage shows has been moved into a fast-track approvals regime, signalling the company is trying to balance a slower, complex Chilean permitting path with quicker-turnaround North American growth.

    With an estimated all-in sustaining cost of about $680/oz at Lobo-Marte, Kinross is positioning this Atacama project in the lower half of the cost curve among the gold projects in our database, which could help buffer margins against Chile’s higher regulatory and environmental compliance costs.

    The planned 220 kV transmission line echoes other recent items in our database where governments are funding high-capacity lines for mining (e.g. Ontario’s Ring of Fire), suggesting that securing grid-scale power is becoming a central design and permitting issue for large gold and copper projects rather than an afterthought.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Northern Star March gold surge: ramp-up implications for mine planners and contractors
    Mining
    about 2 hours ago

    Northern Star March gold surge: ramp-up implications for mine planners and contractors

    Northern Star Resources’ March quarter gold sales have surged, signalling a production ramp-up across its Western Australian assets including Kalgoorlie Consolidated Gold Mines and the Super Pit. Management is positioning for record output in FY25–26 as processing throughput and mine development advance at key hubs such as Yandal and Pogo, supported by higher mill utilisation and improved grade control. For contractors and suppliers, the trajectory points to increased demand for underground development, open-pit fleet capacity, and plant optimisation services over the next 12–18 months.

    Ausenco EPCM at Hillside copper project: design and risk notes for engineers
    Mining
    about 2 hours ago

    Ausenco EPCM at Hillside copper project: design and risk notes for engineers

    Ausenco has secured an engineering, procurement and construction management (EPCM) contract for the Hillside copper project, signalling progression towards full project execution after a prolonged permitting and feasibility phase. The mandate covers process plant design, materials handling and associated infrastructure, positioning Ausenco to define key specifications for concentrator throughput, tailings management and power supply. For geotechnical and civil teams, the EPCM scope will drive final decisions on pit geotechnics, foundation systems for heavy plant and haul road geometry ahead of construction mobilisation.

    ION Minerals lithium brine expansion: resource scale and project lens for engineers
    Mining
    about 3 hours ago

    ION Minerals lithium brine expansion: resource scale and project lens for engineers

    ION Minerals has expanded its lithium brine portfolio to just over 280,000 mineral acres across the Smackover Formation in East Texas/Arkansas, the Texas Panhandle and Saskatchewan’s Duperow Formation, with adjacent Smackover projects reporting 47–60 tonnes LCE per acre. The company now controls nearly 50,000 acres between Tetra Technologies’ Evergreen Brine Unit and Standard Lithium’s Reynolds and Franklin units, plus 65,000 acres in the Texas Panhandle where internal work suggests up to 2.4 million tonnes LCE in place. A further 165,000 acres in southeast Saskatchewan could host up to 2.5 million tonnes LCE, with multi-bench Duperow drilling and testing scheduled for summer 2026.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.