Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy
    Projects
    Contract Award

    Hudson Tunnel $16bn funding halt: schedule and risk takeaways for engineers

    January 29, 2026|

    Reviewed by Tom Sullivan

    Hudson Tunnel $16bn funding halt: schedule and risk takeaways for engineers

    First reported on New Civil Engineer

    30 Second Briefing

    Work on the $16bn Hudson Tunnel rail project under the Hudson River between New York and New Jersey is set to cease next week after a halt in federal funding, with the White House blaming Democrat resistance to a wider border security deal and “illegal aliens”. The scheme, part of the Gateway Program, includes twin rail tunnels and major approach works designed to increase Amtrak and NJ Transit capacity and rehabilitate the existing 1910 North River Tunnel. A prolonged stop risks contractor demobilisation, schedule slippage and higher costs on complex riverbed and urban tunnelling packages.

    Technical Brief

    • Federal funding interruption is immediate, forcing contractors to plan site shutdown within days.
    • Demobilisation of specialist tunnelling crews and plant risks loss of TBM and marine works continuity.
    • Temporary works in the Hudson River and on rail approaches may need mothballing or partial removal.
    • Existing contracts for early works packages face suspension, with potential claims for standby and remobilisation costs.
    • Procurement of long-lead items (segmental linings, rail systems, power and signalling) may be deferred or renegotiated.
    • Similar large tunnelling schemes show that stop–start funding typically inflates capex and elongates commissioning.

    Our Take

    At a projected US$16bn, the Hudson Tunnel sits at the very top end of project sizes in our 583-item Infrastructure database, meaning any construction halt would strand unusually large sunk design and early-works costs compared with most transport schemes.

    Because the Hudson Tunnel links New York and New Jersey under the Hudson River, a stop–start construction pattern would complicate marine and geotechnical risk management, as temporary works and groundwater controls are harder to maintain safely during prolonged pauses.

    Within our 1,553 tag-matched Projects/Contract Award pieces, very few United States schemes approach this scale, so a politically driven delay here is likely to be watched closely by contractors when pricing risk and escalation on other major Northeast corridor bids.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.