    HS2 tunnelling to Euston: geotechnical risk and monitoring notes for engineers

    January 22, 2026|

    Reviewed by Tom Sullivan

    HS2 tunnelling to Euston: geotechnical risk and monitoring notes for engineers

    First reported on New Civil Engineer

    30 Second Briefing

    HS2’s Skanska Costain Strabag joint venture will start driving the Euston link tunnels from Old Oak Common next week, progressing the underground connection towards the central London terminus. The works will extend the existing Old Oak Common tunnel drives, using large-diameter TBMs to thread beneath dense urban infrastructure and utilities on the approach to Euston. Geotechnical and structural interface risks around existing Network Rail assets and deep foundations will be critical, with settlement control and real-time monitoring likely to dominate construction methodology.

    Technical Brief

    • Settlement management will rely on dense instrumentation arrays and trigger-action-response plans agreed with asset owners.
    • Urban tunnelling beneath utilities demands coordinated utility protection plans and emergency isolation procedures for each major service.
    • TBM operations must comply with confined-space, hyperbaric intervention and pressurised-face safety protocols.
    • Lessons on monitoring density, trigger levels and stakeholder coordination are likely to inform future UK urban tunnelling standards.

    Our Take

    Skanska’s recent heavy-lift work on the 4,200‑tonne Clifton railway bridge in the United Kingdom signals that the Skanska Costain Strabag (SCS) JV is coming into the Euston–Old Oak Common tunnelling phase with very current experience in complex rail interfaces and constrained motorway/rail corridors.

    Our database shows multiple HS2-related items involving the SCS JV trialling graphene‑reinforced 3D‑printed concrete with Versarien; even though Versarien has since entered administration, those trials suggest the JV is actively exploring non-standard concrete solutions that could later be applied to underground works around Euston station.

    Within the 514 Infrastructure stories tracked, Skanska appears frequently on major UK schemes such as the Lower Thames Crossing, indicating that the HS2 project benefits from a contractor base already embedded in UK regulatory and safety regimes, which tends to shorten learning curves for high-risk tunnelling near dense urban assets.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy