Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy
    Projects
    Sustainability

    HS2 Euston tunnel drive: logistics, spoil and segment strategy for engineers

    January 28, 2026|

    Reviewed by Joe Ashwell

    HS2 Euston tunnel drive: logistics, spoil and segment strategy for engineers

    First reported on The Construction Index

    30 Second Briefing

    The first of two Herrenknecht tunnel boring machines for HS2’s Euston Tunnel, 1,624‑tonne “Madeleine”, has begun driving the 4.5‑mile twin‑bore section between Old Oak Common and Euston, the fifth and final deep tunnel on the 140‑mile London–Birmingham route. Contractor Skanska Costain Strabag JV will use the 853‑metre Atlas Road logistics tunnel to supply 48,294 precast concrete ring segments and handle more than 1.5 million tonnes of spoil via conveyor to the Willesden Euro terminal depot. Spoil will then be moved by rail for reuse on schemes in Kent, Cambridgeshire and Warwickshire, reducing HGV movements in west London.

    Technical Brief

    • 1,624‑tonne Herrenknecht TBM “Madeleine” is now cutting the Euston Tunnel from Old Oak Common.
    • Euston Tunnel is the fifth and final deep twin‑bore tunnel on the 140‑mile HS2 London–Birmingham alignment.
    • Skanska Costain Strabag JV has already completed 8.4 miles of twin‑bore tunnelling between West Ruislip and Old Oak Common.
    • Atlas Road logistics tunnel, completed January 2024, is 853 m long and provides access to both Euston TBMs.
    • Logistics tunnel enables underground delivery of 48,294 precast concrete ring segments and extraction of over 1.5 Mt spoil.
    • Conveyors transfer all Euston Tunnel arisings to the London Logistics Hub at Willesden Euro terminal for rail loading.
    • Use of a dedicated logistics tunnel and rail‑based spoil removal offers a replicable model for urban TBM drives.

    Our Take

    With SCS JV already having completed 8.4 miles of twin-bore tunnels under outer London, the Euston Tunnel push suggests HS2 Ltd is now transitioning from peripheral to core urban interfaces, where settlement control and third-party asset protection typically drive up monitoring and mitigation costs.

    The 853 m Atlas Road Logistics Tunnel and plan to move more than 1.5 million tonnes of spoil underground indicate HS2’s London section is leaning heavily on off-street logistics, a pattern in our Infrastructure coverage that usually reduces lorry movements and local air-quality complaints but complicates construction sequencing.

    Herrenknecht’s role on this fifth deep twin-bore tunnel reinforces its position as the go-to TBM supplier on long UK rail drives in our database, which may influence procurement strategies for future underground sections or extensions around Old Oak Common and Euston.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.