    Chimney Hollow ACRD dam delivery: design and construction lessons for engineers

    January 23, 2026|

    Reviewed by Joe Ashwell

    Chimney Hollow ACRD dam delivery: design and construction lessons for engineers

    First reported on New Civil Engineer

    30 Second Briefing

    Construction of the Chimney Hollow Reservoir in Colorado has delivered the US’s largest asphalt-core rockfill dam (ACRD), with main works now complete and the structure built to full height on schedule. Engineers had to manage complex rockfill placement around a central asphalt core, stringent seepage control, and tight temperature and compaction windows for the asphaltic concrete in a high-altitude environment. The project’s performance will be closely watched by dam designers considering ACRD solutions for sites with challenging foundations and seismic demands.

    Technical Brief

    • Asphalt core constructed in narrow central slot, requiring millimetre-level alignment with adjacent rockfill zones.
    • Construction sequencing maintained continuous upstream and downstream rockfill support to limit differential deformation against the asphalt core.
    • Temperature-controlled asphalt batching and insulated transport trucks were used to keep mix within tight placement limits.
    • On-core compaction plant operated on a restricted-width platform, demanding strict traffic management and edge stability control.
    • Instrumentation embedded in the core and shoulders provides continuous monitoring of temperature, deformation and seepage during first filling.
    • Emergency action planning and downstream public-safety coordination were integrated with commissioning to address first-impoundment risk scenarios.
    • Experience at Chimney Hollow is expected to inform US dam-safety regulators’ guidance on future ACRD approvals.

    Our Take

    Within the 517 Infrastructure stories in our database, very few cover advanced concrete-faced or asphalt-core rockfill dams in the United States, so Chimney Hollow reservoir effectively becomes a reference case for large embankment dam delivery under current US regulatory and environmental constraints.

    Safety-tagged project pieces in the US often centre on ageing dam rehabilitation rather than new-build assets, which suggests lessons from Chimney Hollow’s construction sequencing, monitoring and risk management will likely be watched by operators planning upgrades to existing structures in similar seismic and hydrological settings.

    Because New Civil Engineer’s coverage of US projects tends to focus on transport and urban works, a large water-storage asset like Chimney Hollow stands out as an indicator that long-lead water infrastructure is moving back up the priority list for US authorities facing drought resilience and peak-demand concerns.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers
    Infrastructure
    about 1 month ago

    Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers

    Strabag and Group company Züblin have secured the design-and-build structural works for the ABS Gäubahn Nord/Pfaffensteig Tunnel in south-west Germany, centred on an 11km twin-bore rail tunnel linking Stuttgart Airport station directly to the Gäubahn line towards Switzerland. About 9.8km will be driven by two TBMs, with conventional tunnelling for the A8 motorway undercrossing and airport connection, plus a 240m cut-and-cover section, retaining structures, railway underpasses and a grade-separated crossing. A 3km surface section will be upgraded and partially realigned for 200km/h operation, delivered under an integrated project delivery model with Ed. Züblin, Wayss & Freytag and Strabag AG sharing tunnelling, structural and earthworks packages.

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers
    Infrastructure
    3 months ago

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers

    A 271.5‑tonne Herrenknecht Mixshield TBM, Caroline, has started driving a 2.2km electricity cable tunnel with a 4m internal diameter beneath the River Thames in Essex for National Grid’s Grain to Tilbury project, delivered by the Ferrovial BEMO joint venture. The drive will pass through variable Thames estuary ground conditions between 35m‑deep launch and reception shafts of 15m and 12m diameter, with tunnelling continuing into 2026 and overall scheme completion targeted for 2029. The new tunnel will replace the 1969 Thames Cable Tunnel and carry new high‑voltage circuits between Grain and Tilbury substations.

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    4 months ago

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy