    Chimney Hollow ACRD dam delivery: design and construction lessons for engineers

    January 22, 2026|

    Reviewed by Joe Ashwell

    Chimney Hollow ACRD dam delivery: design and construction lessons for engineers

    First reported on New Civil Engineer

    30 Second Briefing

    Construction of the Chimney Hollow Reservoir in Colorado has delivered the US’s largest asphalt-core rockfill dam (ACRD), with main works now complete and the structure built to full height on schedule. Engineers had to manage complex rockfill placement around a central asphalt core, stringent seepage control, and tight temperature and compaction windows for the asphaltic concrete in a high-altitude environment. The project’s performance will be closely watched by dam designers considering ACRD solutions for sites with challenging foundations and seismic demands.

    Technical Brief

    • Asphalt core constructed in narrow central slot, requiring millimetre-level alignment with adjacent rockfill zones.
    • Construction sequencing maintained continuous upstream and downstream rockfill support to limit differential deformation against the asphalt core.
    • Temperature-controlled asphalt batching and insulated transport trucks were used to keep mix within tight placement limits.
    • On-core compaction plant operated on a restricted-width platform, demanding strict traffic management and edge stability control.
    • Instrumentation embedded in the core and shoulders provides continuous monitoring of temperature, deformation and seepage during first filling.
    • Emergency action planning and downstream public-safety coordination were integrated with commissioning to address first-impoundment risk scenarios.
    • Experience at Chimney Hollow is expected to inform US dam-safety regulators’ guidance on future ACRD approvals.

    Our Take

    Within the 517 Infrastructure stories in our database, very few cover advanced concrete-faced or asphalt-core rockfill dams in the United States, so Chimney Hollow reservoir effectively becomes a reference case for large embankment dam delivery under current US regulatory and environmental constraints.

    Safety-tagged project pieces in the US often centre on ageing dam rehabilitation rather than new-build assets, which suggests lessons from Chimney Hollow’s construction sequencing, monitoring and risk management will likely be watched by operators planning upgrades to existing structures in similar seismic and hydrological settings.

    Because New Civil Engineer’s coverage of US projects tends to focus on transport and urban works, a large water-storage asset like Chimney Hollow stands out as an indicator that long-lead water infrastructure is moving back up the priority list for US authorities facing drought resilience and peak-demand concerns.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.