    Cabral Gold’s Cuiú Cuiú project: capex, grades and IRR explained for mine planners

    March 12, 2026|

    Reviewed by Joe Ashwell

    Cabral Gold’s Cuiú Cuiú project: capex, grades and IRR explained for mine planners

    First reported on MINING.com

    30 Second Briefing

    Cabral Gold’s Cuiú Cuiú project in Pará, Brazil, has returned its strongest drill intervals to date at the Jerimum Cima target, with hole DDH372 cutting 25.8 metres at 0.6 g/t Au from 131 metres, including about 3 metres at 285.5 g/t Au within a high-grade central zone surrounded by lower grade stockwork. The project’s updated prefeasibility study outlines 13.6 Mt indicated at 0.5 g/t Au (216,182 oz), 6.4 Mt inferred at 0.34 g/t Au (70,570 oz), initial capex of $37.7 million, a 78% post-tax IRR and 10‑month payback at $2,500/oz. Cabral plans Q4 start-up via a heap leach oxide starter pit at Moreira Gomes, targeting 113,000 oz over 6.2 years, with the share price up over 350% year-on-year.

    Technical Brief

    • Hole DDH372 at Jerimum Cima intersected 25.8 m from 131 m depth, including ultra-high-grade core.
    • The same DDH372 zone correlates with earlier intercepts of 45.6 m at 4.5 g/t and 9.5 m at 5.74 g/t.
    • DDH369 cut 14 m at 0.73 g/t from 211.8 m, including 7.5 m at 1.24 g/t.
    • Jerimum Cima’s high-grade core is interpreted as a discrete zone within broader lower-grade stockwork mineralisation.
    • Cuiú Cuiú lies in Pará’s Tapajós region, historically producing 20–30 Moz placer gold district-wide.
    • Local placer workings at Cuiú Cuiú alone are estimated to have yielded 1.5–2 Moz of alluvial gold.

    Our Take

    On our books, Cuiú Cuiú’s post-tax IRR of 78% with an initial capex of C$37.7 million places Cabral Gold at the aggressive end of Latin American gold project economics, suggesting strong leverage to any further resource growth at Jerimum Cima or Moreira Gomes.

    The indicated and inferred grades at Cuiú Cuiú (around 0.5 g/t and 0.34 g/t) are low relative to many hard-rock gold projects in our Mining coverage, so the very short 10‑month payback implies Cabral is likely banking on scale, low strip, or simple processing rather than head grade to drive returns.

    Being only 25 km from G Mining Ventures’ Tocantinzinho project in Pará gives Cabral Gold optionality around shared infrastructure and a potential future district-scale development model in the Tapajós region, which has already seen an estimated 20–30 million ounces of historical placer output.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    pH7 Technologies’ closed-loop PGM and chalcopyrite leaching: key notes for mine planners
    Mining
    1 day ago

    pH7 Technologies’ closed-loop PGM and chalcopyrite leaching: key notes for mine planners

    Canadian processor pH7 Technologies is expanding its Vancouver facility, backed by up to C$4 million from NRC IRAP, to scale its organo-electrochemical platform that recovers platinum, palladium and rhodium from secondary materials without toxic reagents or tailings wastewater. The commercial plant already processes spent catalytic converters, producing 30,000–40,000 oz of platinum-equivalent PGMs per year under a tolling and offtake model involving partners such as Mitsubishi. pH7 is now piloting electrochemically generated oxidants to heap leach chalcopyrite and other sulphide ores without cyanide, targeting on-site mine deployment within 1–2 years across South America, Africa and Australia.

    Dellner Bubenzer mining brakes: integrated drivetrain design notes for engineers
    Mining
    1 day ago

    Dellner Bubenzer mining brakes: integrated drivetrain design notes for engineers

    Dellner Bubenzer is supplying a wide range of industrial brakes and couplings for mining hoists, slewing drives and belt conveyors, developed in long-term collaboration with OEMs. The company focuses on both service and emergency braking solutions tailored to heavy-duty mining duty cycles and harsh environments, addressing controlled hoisting, precise slewing and high-tension conveyor stopping. For engineers, the key point is an integrated approach to drivetrain and braking design, rather than bolt-on safety systems, across multiple critical mining applications.

    SKRI ‘phytocapture’ at Raygorodok: dust control performance insights for mine engineers
    Mining
    2 days ago

    SKRI ‘phytocapture’ at Raygorodok: dust control performance insights for mine engineers

    China’s Zijin Mining is expanding RG Gold’s Raygorodok operation in Kazakhstan with a $500 million processing plant while deploying SKRI’s ‘phytocapture’ system, planting over 100,000 Scots pines across more than 20 hectares about 1.7 km downwind of the open pit. Supercomputer modelling using regional wind-rose data sets tree species and spacing to form multilayered vegetative barriers, not simple landscaping. SKRI reports particulate-matter reductions above 40%, with the forest belt expected to capture roughly one-third of dust emissions as mining advances towards the barrier.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.