    Failure
    Safety

    BHP Brazil dam collapse ruling: tailings design and liability lessons for engineers

    November 21, 2025|

    Reviewed by Tom Sullivan

    BHP Brazil dam collapse ruling: tailings design and liability lessons for engineers

    First reported on New Civil Engineer

    30 Second Briefing

    The UK High Court has found BHP Group liable for the 2015 failure of the Fundão tailings dam in Mariana, Brazil, which killed 19 people and polluted around 600km of the Rio Doce and coastal waterways. The ruling concerns the collapse of an upstream tailings structure jointly owned via Samarco, which released tens of millions of cubic metres of iron ore waste and devastated multiple downstream communities. The judgment opens the door to large-scale civil claims in England, sharpening scrutiny of tailings design, monitoring and governance for UK-listed miners operating overseas.

    Technical Brief

    • Legal findings scrutinise corporate oversight of tailings design, operation and risk management across multinational ownership structures.
    • Investigation workstreams have centred on failure mode analysis of upstream raises, liquefaction susceptibility and operational controls.
    • Post-failure monitoring has focused on downstream contamination pathways, sediment transport and long-term water quality impacts.
    • Remediation programmes must address stabilisation of remaining deposits, riverine sediment management and progressive ecosystem recovery.
    • For tailings facilities globally, upstream designs now face tighter scrutiny, with stronger expectations on independent review and disclosure.

    Our Take

    Within the 22 Failure/Safety-tagged pieces in our database, this is one of the few involving a UK-headquartered major like BHP Group, signalling that legal and ESG scrutiny is now extending more visibly to top-tier diversified miners rather than just local operators.

    The contamination of roughly 600 km of Brazilian waterways means any subsequent BHP Group tailings or water-management designs will likely face tougher permitting and independent review in Brazil and other host countries, with regulators using this case as a benchmark for ‘worst credible’ failure scenarios.

    For UK- and Australia-based mining engineers, a High Court liability finding tied to an overseas failure increases the practical importance of aligning design, monitoring and emergency planning not only with host-country codes but also with UK/Australian corporate governance and due-diligence standards.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 17 hours ago

    Tapojärvi at Sotkamo Silver mine: continuity and risk notes for production engineers

    Tapojärvi has restarted as main mining contractor at Sotkamo Silver’s underground silver mine in Finland, resuming a role it previously held from 2018 to 2023 under a new agreement signed in June 2025. The contract covers full-scale production mining services, including drilling, blasting, loading and haulage in a familiar orebody and infrastructure, allowing rapid ramp-up using existing site knowledge and established operating procedures. For geotechnical and production engineers, continuity in contractor, ground control methods and equipment fleet should reduce interface risk and support stable output planning.

    STRACON’s Los Bronces tailings dam contract: lifecycle model insights for engineers
    Mining
    about 24 hours ago

    STRACON’s Los Bronces tailings dam contract: lifecycle model insights for engineers

    STRACON has secured an integrated engineering, construction, financing and long-term operations and maintenance contract for the Pérez Caldera Tailings Dam at Anglo American Sur’s Los Bronces copper operation in Chile’s Lo Barnechea district. The scope combines dam design and build with funding and multi-year O&M, signalling a bundled delivery model for critical tailings infrastructure rather than separate EPC and operator contracts. For geotechnical and tailings engineers, this points to growing demand for contractors capable of lifecycle stewardship under Chile’s stringent post-Brumadinho regulatory environment.

    Metso’s third orders for Almalyk copper smelter: design and ramp-up notes for engineers
    Mining
    2 days ago

    Metso’s third orders for Almalyk copper smelter: design and ramp-up notes for engineers

    Metso has booked the third tranche of orders for JSC Almalyk Mining and Metallurgical Complex’s copper smelter project in Uzbekistan, following equipment and project services contracts announced on 9 August 2024. The first two tranches, totalling €146 million, were booked in Q4 2024, with the latest booking covering additional core process equipment and associated services for the greenfield smelter complex. The staged order intake signals a multi-phase build-out where process design, commissioning support and long-lead items will be critical for throughput, energy performance and sulphur capture compliance.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.