Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy
    Projects
    Sustainability

    Akela ABeam precast foundations at Emtec BESS: delivery and risk notes for engineers

    February 24, 2026|

    Reviewed by Joe Ashwell

    Akela ABeam precast foundations at Emtec BESS: delivery and risk notes for engineers

    First reported on The Construction Index

    30 Second Briefing

    Akela Ground Engineering has delivered a full precast foundation system for eight BESS units and two PCS units at Emtec Energy’s Sandwich site in Kent, installing over 800 m of 200 × 200 mm driven precast piles to depths of up to 15 m in under five days and 220 m of ABeam ground beams in a further two days. The pinned-joint ABeam system removed the need for in situ concrete, pile caps, tie bars and follow-on trades, enabling a weather-independent, fully off-site manufactured solution delivered in under eight weeks. Use of Akela’s JX piling fleet cut working platform thickness and excavation volumes, reducing programme risk, site traffic and embodied carbon on a live, congested site with soft superficial deposits and biomass surcharge.

    Technical Brief

    • Foundation system designed to accommodate surcharge from stored biomass in addition to BESS/PCS loads.
    • Variable ground profile included soft superficial deposits over granular bearing strata, driving the choice of driven piles.
    • ABeam’s mechanical pinned joints allow rapid beam alignment and tolerance control without wet concrete adjustment.
    • Precast beams manufactured at Akela’s Glasgow facility, decoupling production from the Kent site programme.
    • JX piling fleet reduced working platform thickness, directly cutting imported fill and muck-away volumes.
    • Reduced excavation and fewer vehicle movements were central to Emtec’s lower-carbon, low-traffic construction objectives.
    • Live, congested site conditions required tightly sequenced piling and beam installation to avoid disrupting other trades.
    • Early engagement between Emtec Utility Services and Akela enabled an off-site manufacture / on-site assembly strategy.

    Our Take

    Among recent UK Infrastructure items in our database, very few feature precast piling installed to depths of around 15 m on such short five‑day programmes, suggesting Akela Ground Engineering is positioning ABeam as a fast‑track option for time‑critical BESS sites.

    Delivering more than 800 m of driven precast piling and over 200 m of ground beams from Akela’s precast facility near Glasgow into Kent underlines how offsite manufacture is starting to stretch typical regional catchments for UK foundation supply chains, which could influence how other BESS developers source civils packages.

    Within the 740 Infrastructure stories and 2037 tag‑matched pieces on Projects and Sustainability, battery storage civil works like Emtec’s BESS project in Sandwich remain a small subset, indicating early movers in specialised foundation systems for BESS may gain a reputational edge as more grid‑scale schemes seek rapid deployment.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.