McLaughlin & Harvey procurement delays: risk and cashflow lessons for project teams
Reviewed by Joe Ashwell

First reported on The Construction Index
30 Second Briefing
Procurement delays on major schemes cut McLaughlin & Harvey Holdings’ turnover by 30% to £612.1m for the year to 30 June 2025, from £870.4m, as multiple large civil engineering and construction projects slipped into mid-to-late 2025/26. Despite the volume hit, operating profit rose to £12.8m and pre-tax profit to £18.2m, with both the Northern Ireland and Scottish construction arms contributing positively. The group reports net assets of £67m, cash of £148m and says most 2025/26 budgeted turnover is already secured in the order book.
Technical Brief
- Procurement-stage prolongation is explicitly delaying commencement of “a number of scale projects” into mid–late 2025/26.
- Management links delays to industry-wide lengthening of tendering and award processes before site mobilisation.
- Directors warn the 2025/26 financial year will again see turnover timing distorted by late starts.
- Cash on hand of £148m provides substantial working-capital cover for long pre-construction and bid periods.
- Net assets of £67m give a relatively strong balance sheet for bonding and framework prequalification.
- Both Northern Ireland and Scottish construction divisions remained profit-contributing despite reduced work-on-site volumes.
- Order book already secures the majority of 2025/26 budgeted turnover, reducing short-term bidding exposure.
Our Take
Despite the 30% turnover drop, McLaughlin & Harvey’s £148m cash balance and £67m net assets give it a stronger liquidity position than many UK regional contractors in our Infrastructure coverage, which should help it ride out delayed public-sector procurements in Scotland and Northern Ireland.
The improvement in profit before tax relative to the previous year, even on lower revenue, suggests McLaughlin & Harvey has tightened cost control and project selection, a pattern also seen in several other UK contractors in our 320 Infrastructure stories as they pivot towards higher-margin frameworks rather than pure volume growth.
With guidance pointing to recovery in the mid to latter stages of the 2025/26 year, the company is likely to be targeting the next wave of UK infrastructure and public building frameworks highlighted across our 820 Projects-tagged pieces, where delayed awards are now starting to move again, particularly in devolved administrations.
Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.
Related Articles
Related Industries & Products
Construction
Quality control software for construction companies with material testing, batch tracking, and compliance management.
Mining
Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.
QCDB-io
Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.