Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy
    Projects

    Hanoi Metro tunnel excavation completed: design and TBM notes for engineers

    December 4, 2025|

    Reviewed by Joe Ashwell

    Hanoi Metro tunnel excavation completed: design and TBM notes for engineers

    First reported on Tunnels & Tunnelling International – News

    30 Second Briefing

    TBM Than Toc (Speedy God), a 6.6m-diameter, 100m-long, 850t Herrenknecht machine operated by Ghella, has broken through at Station S12 (Hanoi Station) after a 4km drive installing 1,720 precast segments on Hanoi Metro Line 3. The 12.5km Pilot Light Line 3, Hanoi’s first underground metro, comprises 8.5km of elevated track, 4km of twin-bore tunnels and four underground stations between Nhon and Hanoi Station, and is now over 72% complete. A second TBM, Tao Bao, is currently advancing towards Station S11, maintaining underground excavation momentum.

    Technical Brief

    • Four underground stations – Kim Ma, Cat Linh, Van Mieu and Hanoi – define intermediate access, ventilation and emergency egress nodes along the 4km tunnel.
    • Alignment connects Nhon in Tay Tuu (Nam Tu Liem district) to Hanoi Station, traversing dense urban fabric with associated settlement and utility protection constraints.
    • Elevated–underground interface over 12.5km requires transition structures managing stiffness contrast, groundwater ingress and differential settlement at portal zones.
    • With >72% overall completion, remaining works are likely dominated by station fit-out, MEP integration and systems testing rather than primary excavation.
    • Second TBM Tao Bao advancing toward Station S11 allows parallel headings, shortening programme and distributing settlement risk over time.
    • Experience from this first underground metro in Hanoi will inform design baselines for subsequent tunnelling under similar geotechnical and urban conditions.

    Our Take

    Herrenknecht’s use on Hanoi’s Line 3 adds to a pattern in our database where the same supplier is also providing large TBMs and vertical shaft sinking machines for European power and metro tunnels, signalling its consolidation in complex urban underground works.

    With only 4km of underground tunnel against 8.5km of elevated track on Line 3, Hanoi is following the cost-optimised alignment mix seen in several Asian metros, which typically reserve full TBM drives for the most constrained central corridors.

    Among the 154 Infrastructure stories in our coverage, Line 3’s >72% completion status puts it in the more advanced tier of urban rail projects, meaning procurement and construction risk for contractors like Ghella is now largely replaced by interface, systems integration and commissioning risk.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers
    Infrastructure
    in 8 months

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers

    A 271.5‑tonne Herrenknecht Mixshield TBM, Caroline, has started driving a 2.2km electricity cable tunnel with a 4m internal diameter beneath the River Thames in Essex for National Grid’s Grain to Tilbury project, delivered by the Ferrovial BEMO joint venture. The drive will pass through variable Thames estuary ground conditions between 35m‑deep launch and reception shafts of 15m and 12m diameter, with tunnelling continuing into 2026 and overall scheme completion targeted for 2029. The new tunnel will replace the 1969 Thames Cable Tunnel and carry new high‑voltage circuits between Grain and Tilbury substations.

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 8 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 7 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Related Industries & Products

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.