    Chile lithium dispute: project, capex and schedule risks for mine planners

    April 6, 2026|

    Reviewed by Joe Ashwell

    Chile lithium dispute: project, capex and schedule risks for mine planners

    First reported on MINING.com

    30 Second Briefing

    France’s Eramet and Chile’s state miner ENAMI are heading to court over the Salares Altoandinos lithium project, a Cold War-era CEOL licensing relic now colliding with Eramet’s 1,200 sq. km of claims covering 99% of the La Isla and Aguilar salt flats in the Atacama. ENAMI has selected Rio Tinto’s $415 million bid, which includes its direct lithium extraction process and access to the Rincon pilot plant, for a project estimated at 4.5 million tonnes lithium and $3 billion capex. A dispute lasting up to two years, possibly moving to international arbitration, could delay Chile’s plan to double lithium output to about 500,000 tonnes annually by 2035 and complicate Kast’s new mining agenda.

    Technical Brief

    • Cold War-era CEOL regime means lithium extraction needs a special state permit, unlike other brine minerals.
    • Eramet’s 1,200 sq. km of concessions cover 99% of La Isla and Aguilar salars in Atacama.
    • ENAMI-Rio Tinto JV capex exceeds $3 billion, with Rio’s bid including $415 million in cash and technology.
    • Eramet is filing easement and water-extraction applications over the project area to reinforce its concession leverage.
    • Legal challenges to Rio Tinto’s selection could run at least two years and may escalate to international arbitration.
    • Chilean lawyers warn ENAMI’s choice of a partner without underlying claims risks being interpreted as de facto expropriation.
    • Eramet is now signalling interest in co-extracting boron, iodine and potassium from the same brines as lithium.
    • CleanTech Lithium secured Chile’s first private CEOL at Laguna Verde in 2023, largely due to near-100% claim coverage.

    Our Take

    With Salares Altoandinos estimated to host about a quarter of Chile’s lithium resources and CleanTech Lithium’s Laguna Verde PFS targeting 15,000 t/y over 25 years, our database suggests that disputes over Atacama-region tenure now touch both mega-scale state-linked projects and smaller DLE-focused juniors, complicating long-term supply planning for battery-metal offtakers.

    Eramet’s $900 million Centenario facility in northwest Argentina and its IRMA-audited Grande Côte operation in Senegal indicate the group is positioning itself as a ‘responsible’ large-scale producer; any prolonged Chilean legal stand-off could push Eramet to prioritise jurisdictions where ESG credentials and permitting pathways are clearer.

    The projected ability of Salares Altoandinos to supply lithium for 1.5 million EVs per year by 2035, set against only a handful of other lithium mega-projects in our 1209 Mining stories, means that multi-year court delays would likely tighten the pipeline of Tier-1 brine projects just as downstream policy in the US and EU is trying to diversify away from existing suppliers.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    The Metals Royalty Nasdaq debut: deep-sea nodule economics for mine financiers
    Mining
    about 16 hours ago

    The Metals Royalty Nasdaq debut: deep-sea nodule economics for mine financiers

    The Metals Royalty Company has listed on Nasdaq under ticker TMCR, offering investors a royalty exposure to TMC’s NORI deep-sea polymetallic nodule project in the Pacific Ocean targeting nickel, cobalt and copper. Chief executive Brian Paes-Braga positions the structure as a conventional mining royalty model applied offshore, with returns linked to future production from nodules on the Clarion-Clipperton-type seabed rather than equity in TMC (NASDAQ: TMCWW). For mining financiers and project developers, the move signals growing capital-market appetite for seabed resource plays despite unresolved regulatory and production-risk questions.

    Uranium Energy’s Burke Hollow ISR start: production and wellfield notes for engineers
    Mining
    about 17 hours ago

    Uranium Energy’s Burke Hollow ISR start: production and wellfield notes for engineers

    Uranium Energy Corp has started production at its Burke Hollow project in Texas, the first new US in-situ recovery (ISR) uranium operation in more than a decade and now the country’s largest ISR wellfield, with measured and indicated resources above 6.15 million lb on a 20,000-acre property. The Vancouver-based miner now runs two active ISR operations, adding Burke Hollow to Christensen Ranch in Wyoming, with a third planned at Ludeman next year. ISR solutions from Burke Hollow will be piped to the Hobson Central Processing Plant, licensed for up to 4 million lb U₃O₈ per year.

    First Quantum–IFC Taca Taca deal: capex, standards and risks for mine planners
    Mining
    about 18 hours ago

    First Quantum–IFC Taca Taca deal: capex, standards and risks for mine planners

    First Quantum Minerals has partnered with the International Finance Corporation to align the Taca Taca copper project in Salta Province, Argentina, with IFC Performance Standards on Environmental and Social Sustainability, a move aimed at improving access to debt financing. The open-pit project is scoped for 40 Mtpa throughput with expansion potential to 60 Mtpa, requiring about $4.2–5.25 billion in capex and targeting roughly 291,000 tonnes of copper per year over the first decade of a 35‑year mine life. Construction is expected to create up to 4,000 jobs and 2,000 operational roles, with IFC emphasising local skills development and infrastructure build‑out.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.