    Rare Earths Norway €24m Fen pilot plant: flowsheet and zoning notes for mine planners

    November 5, 2026|

    Reviewed by Tom Sullivan

    Rare Earths Norway €24m Fen pilot plant: flowsheet and zoning notes for mine planners

    First reported on MINING.com

    30 Second Briefing

    Rare Earths Norway has approved a €24-million pilot plant at Ulefoss to test an integrated ore-to-rare-earth-oxide flowsheet for the Fen deposit, which holds 123 million indicated tonnes at 1.35% TREO plus 1.08 billion inferred tonnes at 1.31% TREO. The plant, housed in an existing industrial building and targeting 6,000 tonnes of ore over three years, is slated to start up in Q3 2027 with funding support from Innovation Norway, the Telemark Development Fund and EIT RawMaterials. Design changes include increasing the protective rock cover above underground openings from 25 m to 100 m, while a state-led zoning process aims to fix mine, plant, tailings and infrastructure locations by 2028.

    Technical Brief

    • Protective rock cover between underground workings and surface increased fourfold, from 25 m to 100 m.
    • Resource update effective 31 December nearly doubled contained oxides to 15.9 million tonnes.
    • Indicated resource now 123 Mt TREO, with neodymium–praseodymium oxides forming about 19% of TREO.
    • Inferred resource totals 1.08 Bt at 1.31% TREO, containing 14.2 Mt rare earth oxides.
    • Approximately 30,000 m of drill core logged and assayed, including 10,000 m from the latest campaign.
    • Zoning process, taken over by Norway’s government in April, targets completion by 2028.
    • National zoning will fix locations and conditions for underground mine, processing plant, tailings and associated infrastructure.

    Our Take

    With 19% of Fen’s rare earth oxides in NdPr, as highlighted in the March 2026 resource update, Rare Earths Norway is positioning this Norwegian asset in the same high-value magnet segment that LKAB’s Per Geijer project targets, which could sharpen competition for EU downstream magnet and motor manufacturers.

    The roughly 80% jump in contained oxides at the Fen deposit since the earlier 2024 figure, referenced in our prior coverage, means the €24-million pilot is effectively de-risking flowsheet and permitting for what now screens as one of Europe’s larger rare earth inventories rather than a marginal test asset.

    Norway’s backing via Innovation Norway and the Telemark Development Fund, combined with EIT RawMaterials’ EU-level involvement, signals that Fen is being treated as a strategic rare earths project for Europe, in contrast to many of the smaller rare earth items in our database that lack this kind of coordinated national–EU support.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Eagle Nuclear–Noble Plains deal: ISR uranium resource and drilling lens for engineers
    Mining
    about 1 hour ago

    Eagle Nuclear–Noble Plains deal: ISR uranium resource and drilling lens for engineers

    Eagle Nuclear Energy has signed a binding all‑stock LOI to acquire 100% of Noble Plains Uranium at a deemed C$0.125 per share, a 92% premium to Noble Plains’ 29 October TSXV close, with Noble Plains shareholders to hold about 4.78% of the combined equity. The deal adds ISR‑amenable projects in Wyoming, including the Duck Creek project in the Powder River basin with 5.32M lbs U₃O₈ Indicated and 1.04M lbs Inferred (NI 43‑101) over only 2.5 miles of a 5.25‑mile trend. Eagle plans a 12–18 month phased exploration programme targeting deeper mineralised formations and further resource growth around existing ISR infrastructure.

    Mining
    about 1 hour ago

    Freeport’s US$4.5bn Bagdad expansion: design and haulage notes for mine planners

    Freeport-McMoRan has approved a US$4.5 billion brownfield expansion and modernisation of its wholly owned Bagdad copper–molybdenum mine in northwest Arizona, aiming to more than double current mining and milling rates. The plan includes enlarging the autonomous haulage system (AHS) truck fleet and installing a new overland conveyor to move higher tonnages from pit to plant, reducing reliance on truck haulage. For mine planners and geotechs, the scale-up will drive larger pit pushbacks, higher waste movement and updated slope, haul road and dump designs.

    Western tungsten price gap to China: supply and DFARS lens for mine planners
    Mining
    about 1 hour ago

    Western tungsten price gap to China: supply and DFARS lens for mine planners

    Western ammonium paratungstate (APT) prices have blown out to 3.74 times China’s, with Rotterdam warehouse APT at $278.22/kg in October versus $74.43/kg China ex-works, after China’s February 2025 export licensing and higher US tariffs fractured what was previously a 1.24x premium market. Since February 2025, Rotterdam APT has jumped from $34.60/kg to around $290/kg while China ex-works rose only to about $86/kg, and between March–September 2026 China prices fell 58% as Rotterdam rose 39%, confirming decoupled markets. For mining and downstream processors, the key constraints are now qualified, DFARS-compliant conversion capacity and traceable scrap within US and European supply chains ahead of the 1 January 2027 DFARS procurement restriction.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental