Electric Volvo haulers at Lower Thames Crossing: cost and duty-cycle notes for engineers
Reviewed by Joe Ashwell

First reported on The Construction Index
30 Second Briefing
Four battery-powered Volvo A40 Electric articulated dump trucks, each rated for a 39‑tonne payload, have entered commercial service on National Highways’ Lower Thames Crossing works near East Tilbury, in the first global fleet deployment of this weight class. Operated by Bouygues–Murphy JV, the haulers are fast‑charged from GeoPura hydrogen-fuelled generators via demountable battery packs along the haul route, taking about 40 minutes to go from 20% to 80% state of charge and sustaining eight‑hour shifts. Project forecasts point to lower whole‑life costs than diesel or HVO units through reduced maintenance and cheaper, domestically sourced energy.
Technical Brief
- Hydrogen-fuelled GeoPura generator bank supplies electricity to multiple large, demountable buffer batteries along the haul.
- Demountable battery packs are positioned strategically on the route so haulers can plug-in during natural breaks.
- BMJV uses the A40 Electric units for road foundation build-up and tunnel portal approach works near East Tilbury.
- Volvo A40 Electric payload is specified at 39 tonnes; the smaller A30 Electric variant is rated at 29 tonnes.
- Manufacturer states up to six hours operation per full charge, depending on duty cycle and site conditions.
- Volvo CE is building both A40 and A30 Electric at its Braås, Sweden articulated hauler plant.
- Braås facility previously produced “Gravel Charlie” in 1966, cited as the industry’s first articulated hauler.
- OEM and contractor view the Lower Thames Crossing deployment as a proof-of-scale for heavy civil electrification.
Our Take
Across our infrastructure coverage, Volvo Construction Equipment appears frequently in product-led pieces, and the Lower Thames Crossing deployment of A40 Electric units extends that pattern from award-winning digital platforms like Volvo Co‑Pilot into full heavy-haul electrification on a major UK project.
The 40-minute charge from 20–80% state of charge and up to six hours’ operating time suggest that on constrained sites like East Tilbury, planners will need tightly scheduled charging windows and possibly redundant units to maintain continuous muck-shift cycles at 39 t payloads.
With other recent Volvo articles in our database highlighting electric excavators working in groundwater protection zones, the use of battery haulers on the Lower Thames Crossing signals that zero-emission plant is now being proven on both environmentally sensitive and high-throughput civil works, which will influence future UK tender specifications for contractors such as BMJV.
Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.
Related Articles
Related Industries & Products
Construction
Quality control software for construction companies with material testing, batch tracking, and compliance management.
Mining
Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.
QCDB-io
Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.