Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    Projects
    Research
    Sustainability

    DESNZ underground cable report: cost and method insights for UK grid engineers

    June 15, 2026|

    Reviewed by Joe Ashwell

    DESNZ underground cable report: cost and method insights for UK grid engineers

    First reported on The Construction Index

    30 Second Briefing

    Ramboll’s DESNZ-commissioned study on undergrounding high-voltage transmission lines finds that cable ploughing, horizontal directional drilling and microtunnelling (pipe jacking) can approach the costs of conventional cut-and-cover over 20–50 km routes. Cable ploughing, already used in Wales by Aneurin Thomas Plant with Foeck equipment in sensitive environments, could cut total project costs by 20–40%, with civil works alone reduced by up to 66–72%. The report points to further savings from emerging technologies, including graphene-enhanced conductors and improved converter station design.

    Technical Brief

    • Ramboll benchmarked cut-and-cover against seven trenchless methods: ploughing, HDD, microtunnelling, auger boring, Direct Pipe, E-Power Pipe and Pipe Express.
    • Assessment horizon focused on 20 km and 50 km transmission routes, targeting long-distance undergrounding economics.
    • Methodology combined a literature review with qualitative scoring against capital cost, technical feasibility, environmental impact and completeness of solution.
    • Evidence base relied on published performance and cost claims for both construction methodologies and associated cable technologies.
    • Cable ploughing, HDD and microtunnelling were identified as the only alternatives with route-length cost profiles comparable to cut-and-cover.
    • Application example: Aneurin Thomas Plant has deployed Foeck cable ploughing equipment in environmentally sensitive Welsh sites.
    • Scope is limited by reliance on secondary data and by current UK experience largely confined to short sections.

    Our Take

    DESNZ’s involvement here lines up with other UK energy security work in our database, such as its Wylfa nuclear and gas storage/FSRU assessments, signalling that underground cable cost reductions could directly influence grid-connection strategies for future large generation and storage schemes.

    The 20–50km study route lengths and 20–40% overall cost reductions suggest cable ploughing could materially change the business case for medium-distance onshore transmission reinforcements in the UK, especially where visual impact concerns are pushing projects away from overhead lines.

    Civil engineering cost cuts of 66–72% are significant enough that UK infrastructure clients already working with Ramboll on highways and water quality schemes may start to view ploughed undergrounding as a standard option in multi-utility corridors, rather than a niche technique.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers
    Infrastructure
    about 1 month ago

    Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers

    Strabag and Group company Züblin have secured the design-and-build structural works for the ABS Gäubahn Nord/Pfaffensteig Tunnel in south-west Germany, centred on an 11km twin-bore rail tunnel linking Stuttgart Airport station directly to the Gäubahn line towards Switzerland. About 9.8km will be driven by two TBMs, with conventional tunnelling for the A8 motorway undercrossing and airport connection, plus a 240m cut-and-cover section, retaining structures, railway underpasses and a grade-separated crossing. A 3km surface section will be upgraded and partially realigned for 200km/h operation, delivered under an integrated project delivery model with Ed. Züblin, Wayss & Freytag and Strabag AG sharing tunnelling, structural and earthworks packages.

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers
    Infrastructure
    3 months ago

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers

    A 271.5‑tonne Herrenknecht Mixshield TBM, Caroline, has started driving a 2.2km electricity cable tunnel with a 4m internal diameter beneath the River Thames in Essex for National Grid’s Grain to Tilbury project, delivered by the Ferrovial BEMO joint venture. The drive will pass through variable Thames estuary ground conditions between 35m‑deep launch and reception shafts of 15m and 12m diameter, with tunnelling continuing into 2026 and overall scheme completion targeted for 2029. The new tunnel will replace the 1969 Thames Cable Tunnel and carry new high‑voltage circuits between Grain and Tilbury substations.

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    4 months ago

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy