    Cowi’s 5.3 km Iceland road tunnel: design and risk notes for tunnel engineers

    February 23, 2026|

    Reviewed by Joe Ashwell

    Cowi’s 5.3 km Iceland road tunnel: design and risk notes for tunnel engineers

    First reported on New Civil Engineer

    30 Second Briefing

    Cowi has secured the preliminary and detailed design contract from the Icelandic Road and Coastal Administration (Vegagerðin) for a new 5.3km road tunnel in northern Iceland, set to improve all‑weather connectivity on a key regional route. The long single-bore tunnel will demand detailed geotechnical characterisation of volcanic and glacially influenced ground, plus robust drainage and lining design for sub‑Arctic freeze–thaw conditions. Designers will need to address ventilation, fire and evacuation provisions consistent with European road tunnel standards, with constructability in remote terrain a central constraint.

    Technical Brief

    • Contract scope covers both preliminary and detailed design phases under a single appointment.
    • Safety-by-design focus is expected to influence cross-section geometry, refuge spacing and systems redundancy.

    Our Take

    Among the 737 Infrastructure stories in our coverage, Iceland features only rarely, so a 5.3km tunnel in northern Iceland signals one of the more substantial transport interventions in a low-population, high‑hazard environment.

    Cowi appears frequently in our Projects and Safety‑tagged items as a preferred designer for long Nordic tunnels, suggesting Vegagerðin is leaning on established Scandinavian rock engineering and ventilation expertise for this scheme.

    For a 5.3km road tunnel in northern Iceland, long-term resilience to snow, ice ingress and rock freeze–thaw will likely dominate the design brief, which tends to push clients towards conservative linings, robust drainage and high-spec life‑safety systems compared with shorter temperate‑climate tunnels in our database.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.