Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    Projects

    Artemis Gold’s Blackwater mill cost rise: capacity, capex and schedule for engineers

    August 5, 2026|

    Reviewed by Tom Sullivan

    Artemis Gold’s Blackwater mill cost rise: capacity, capex and schedule for engineers

    First reported on MINING.com

    30 Second Briefing

    Artemis Gold has lifted the cost of its first Blackwater mill expansion in central British Columbia to C$120 million, about 20% above the original C$100–C$110 million budget, to add spares and raise nameplate capacity by one‑third to 8 million tonnes per year. The revised spend equates to roughly C$60 per tonne of added annual capacity, with civil works for a new vertical mill complete, structural steel advancing, pre‑aeration tank erected and oxygen equipment foundations poured as mechanical tie‑ins to the live plant now dictate schedule. A much larger C$1.44‑billion second expansion would add a separate 13‑million‑tonne‑per‑year plant, targeting total 21‑million‑tonne capacity and more than 500,000 oz. of gold annually from 2029, positioning Blackwater among Canada’s largest gold operations.

    Technical Brief

    • Civil works for the new vertical mill are complete, with structural steel erection underway.
    • Pre-aeration tank is already erected and oxygen equipment foundations poured ahead of mechanical tie-ins.
    • A new cyclone cluster is in transit to site, with mill components starting to arrive.
    • Mechanical installation and tie-ins to the live plant now form the critical path for schedule.
    • Site construction was 57% complete as of 30 June, with Q4 start-up of the expanded circuit targeted.
    • First expansion overrun sits within 2026 growth capital of C$670–C$745 million, funded from operations.
    • Blackwater produced 74,063 oz. in Q2, up 20% quarter-on-quarter, with H1 output at 135,986 oz.
    • A failed ball mill gearbox in March caused an unplanned shutdown, but subsequent quarter delivered record output.
    • 2023 commercial production totalled 192,808 oz. at an all-in sustaining cost of US$869/oz sold.
    • Artemis holds C$175 million cash plus an undrawn C$700 million revolver, supporting concurrent expansion and operations.

    Our Take

    The March 2026 gearbox failure at Blackwater in our database underscores that Artemis Gold is managing both reliability issues and a 20% mill expansion cost overrun at the same asset, which will likely sharpen lender and board scrutiny of contingency and spares strategies for the 21 Mtpa build‑out.

    Within our 1269 Mining stories, Artemis Gold appears frequently alongside other British Columbia gold operators such as Osisko Development and Centerra Gold, signalling that capital intensity and permitting risk in central B.C. are becoming a comparative lens for investors assessing large gold projects like Cariboo versus Blackwater.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Fremont NPV jumps 101%: project economics and risk notes for mine planners
    Mining
    about 5 hours ago

    Fremont NPV jumps 101%: project economics and risk notes for mine planners

    Stormlands Mining’s decision-intelligence case study on Lode Gold Resources’ Fremont project in Mariposa County, California, doubles the modelled NPV to US$511.5 million by applying a gold price of US$4,245.22/oz to the project’s 2026 technical report. The revised scenario lifts projected life-of-mine revenue from US$3.45 billion to US$4.17 billion, increases IRR from 11.16% to 16.66%, and shortens payback from 8.5 years to 5 years 11 months at a 5% discount rate. Fremont, a 13.56 km² property with historical grades of 10.7 g/t Au, is being drilled ahead of a 2027 pre-feasibility study.

    Lion Copper’s Yerington copper portfolio: scale, capex and PFS lens for mine planners
    Mining
    about 5 hours ago

    Lion Copper’s Yerington copper portfolio: scale, capex and PFS lens for mine planners

    Lion Copper & Gold’s Bear deposit at the Rio Tinto-backed Yerington project in Nevada has an initial resource of about 1.0 billion indicated tonnes at 0.29% copper (6.7 billion lb) and 1.7 billion inferred tonnes at 0.22% copper (8.7 billion lb), making it one of the state’s largest undeveloped copper resources. Combined with Yerington’s 506.6 million tons of proven and probable reserves at 0.21% copper (2.1 billion lb), Lion’s Nevada portfolio now totals roughly 19 billion lb of contained copper, surpassing Hudbay’s Mason and Pumpkin Hollow. A 2025 PFS outlined 120 million lb/year cathode output over 12 years, with a post-tax NPV7 of US$694 million, 14.6% IRR and US$724 million initial capex, while Rio Tinto’s Nuton continues heap-leach testing under its 65% earn-in option.

    Myanmar rare earth mining boom: slope failure and leach risks for engineers
    Mining
    about 5 hours ago

    Myanmar rare earth mining boom: slope failure and leach risks for engineers

    War-fractured Myanmar has become the world’s largest supplier of heavy rare earths, with Chinese companies running largely unregulated in-situ leaching operations in autonomous border regions such as Kachin and eastern Shan, guarded by ethnic armies including the United Wa State Army. Workers like “Min” are paid about 3,000 yuan (£330) per month for roadbuilding and pit work on steep slopes, amid frequent fatal landslides and exposure to toxic lixiviants that have poisoned rivers and farmland. Ore is trucked into China, mixed with other feedstocks and effectively laundered into global supply chains for EVs, wind turbines and advanced weapons, while revenues fund more than 1,200 armed groups in an already fragmented civil war.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy