    AFRY EPCM at Cabaçal project: design and constructability notes for mine engineers

    November 19, 2026|

    Reviewed by Joe Ashwell

    First reported on International Mining – News

    30 Second Briefing

    AFRY will deliver full engineering, procurement and construction management (EPCM) services for Rio Cabaçal Mineração’s Cabaçal copper-gold-silver project in Mato Grosso, Brazil, a key asset of Meridian Mining. The mandate covers process plant, mine infrastructure and associated utilities, positioning AFRY to define flowsheets, specify major equipment packages and coordinate construction sequencing. For engineers, the contract signals upcoming demand for detailed geotechnical design, tailings and water management solutions, and constructability planning suited to remote Central Brazilian conditions.

    Technical Brief

    • EPCM scope is expected to extend from open-pit mine design through to surface infrastructure and utilities.
    • AFRY’s remit typically includes detailed earthworks design for plant platforms, haul roads and drainage.
    • Contract structure allows integration of geotechnical, hydrological and structural inputs into a single coordinated 3D model.
    • Central Mato Grosso location implies logistical constraints for heavy equipment delivery and construction materials supply.
    • Remote setting will drive emphasis on self-sufficient power, water supply and on-site maintenance facilities.
    • Brazilian permitting regime will require alignment of EPCM design deliverables with federal and Mato Grosso state licensing stages.
    • Tailings and water management designs must account for intense seasonal rainfall and potential flood routing.
    • For similar greenfield mining projects, early EPCM engagement often compresses schedule by overlapping design and procurement.

    Our Take

    AFRY’s EPCM role at the Cabaçal copper-gold-silver project in Mato Grosso follows Meridian Mining’s move into pre-construction there, where more than twenty financing proposals of up to $400 million have been shortlisted, signalling that detailed engineering and constructability input will now be critical to closing a funding package.

    AFRY’s planned acquisition of Australian Mining Consultants (AMC) suggests that its work on Cabaçal in Brazil could be backed by an enlarged in-house capability across resource definition, mine planning and operations support, rather than a pure process-plant focus.

    In our database of 1279 Mining stories, copper- and gold-tagged projects like Cabaçal increasingly feature multi-commodity profiles (here including silver), which typically improves financing optionality but complicates metallurgical design and marketing strategies for operators such as Meridian Mining.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    Cancel at any time.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 1 hour ago

    CPS Chile composite roller plant: design and energy notes for mine conveyors

    CPS Conveyor Products and Solutions is opening a dedicated composite conveyor roller manufacturing plant in Santiago, Chile, claimed to be the first facility of its kind in the country. The plant will supply lightweight, corrosion‑resistant composite idlers tailored to long overland and high‑capacity mine conveyors in the Andean region, reducing freight lead times from overseas suppliers. For operators, local production should simplify spares logistics, support faster change‑outs on critical belts, and enable designs that cut rotating mass and energy draw compared with traditional steel rollers.

    Collective’s Apollo waste halo: pit optimisation and mill feed upside for engineers
    Mining
    about 1 hour ago

    Collective’s Apollo waste halo: pit optimisation and mill feed upside for engineers

    Collective Mining has intersected near-surface gold and silver in material previously classed as waste within the planned Apollo open pit at Guayabales, Colombia, including 107.85 metres at 0.79 g/t gold and 14 g/t silver from 3.75 metres and 146.1 metres at 0.66 g/t gold, 19 g/t silver and 0.04% copper from 106.5 metres, extending up to 60 metres beyond the current resource shell. National Bank of Canada estimates the shallow halo drilling now covers about 45% of the zone, averaging 0.83 g/t AuEq over 42.4 metres, suggesting scope to convert waste to mill feed and re-optimise pit economics. Collective plans US$100 million of Colombian spend in 2027, targeting a resource update in late 2027/early 2028 and an environmental licence application for Apollo in H2 2027, while AngloGold Ashanti advances the adjacent US$2.5 billion Quebradona copper project towards potential 2028 construction.

    Phoenix at Lexington mine: drill results and open-pit potential for engineers
    Mining
    about 1 hour ago

    Phoenix at Lexington mine: drill results and open-pit potential for engineers

    Phoenix Metals has reported broad mineralised intervals at the historic Lexington mine in southern British Columbia, with hole LXDDH-26-001 cutting 169 m from 41 m depth grading 1.02 g/t gold, 0.22% copper and 3.79 g/t silver, including a 38 m higher-grade zone. A second hole returned 233.5 m from 8.5 m depth at 0.26 g/t gold, 0.14% copper and 0.86 g/t silver, while two further holes averaged 0.18–0.20 g/t gold over more than 180 m each. Phoenix has outlined a 1.5 km by 300 m exploration footprint from 20 new holes (6,350 m) plus 170 historical holes, but must complete a resource estimate and economic study to assess open-pit viability.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental