Geomechanics.io

  • Free Tools
Sign UpLog In

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    Projects
    Contract Award

    RWE completes Camster II wind farm: delivery and design notes for engineers

    April 24, 2026|

    Reviewed by Joe Ashwell

    RWE completes Camster II wind farm: delivery and design notes for engineers

    First reported on The Construction Index

    30 Second Briefing

    RWE has completed the 36 MW Camster II onshore wind farm in Caithness, comprising 10 turbines and enough capacity to supply electricity equivalent to about 51,000 typical homes, as the first of four new Scottish RWE onshore projects totalling up to 232 MW. Principal contractor Farrans supported over 50 construction roles, took on two early careers civil engineering students and an apprentice, and sourced 54% of subcontractors within 20 miles of the site, including Gow Earthworks, GMR Hendersons and John Gunn and Sons. Operations and maintenance will be handled by locally based engineers, consolidating a regional wind cluster that now includes four operational RWE farms in Caithness.

    Technical Brief

    • Consent for Camster II was granted in July 2021, with physical construction commencing in 2023.
    • Grid export began with first power in March 2026, prior to full commissioning.
    • Ten-turbine layout implies an average installed capacity of 3.6 MW per unit.
    • Camster II is the first of four new Scottish RWE onshore projects totalling up to 232 MW.
    • RWE now operates four wind farms in Caithness, forming a concentrated regional generation cluster.
    • Farrans’ subcontractor strategy kept 54% of firms within 20 miles, equating to 56% of spend.
    • Local O&M resourcing is intended to provide long-term engineering roles tied to asset life.
    • Ongoing collaboration between RWE and Farrans continues at the Golticlay wind farm, supporting delivery continuity.

    Our Take

    RWE’s completion of the 36 MW Camster II in Caithness sits alongside its recent UK power purchase agreement with Network Rail, signalling that RWE is building both generation capacity and long-term offtake in the UK power market rather than relying solely on merchant exposure.

    With Camster II contributing to a 232 MW pipeline of four new onshore wind farms in Scotland, RWE is consolidating a material onshore footprint in a region where our infrastructure coverage has more often focused on transport and building projects than grid‑connected renewables.

    The fact that 54% of subcontractors on Camster II were sourced within 20 miles of the site, and accounted for 56% of subcontract spend, reinforces a pattern seen in our database where Scottish onshore wind schemes increasingly lean on local civils firms such as Farrans to bolster social licence and planning narratives for future phases.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers
    Infrastructure
    in 7 months

    National Grid TBM under the Thames: tunnelling design and risk notes for engineers

    A 271.5‑tonne Herrenknecht Mixshield TBM, Caroline, has started driving a 2.2km electricity cable tunnel with a 4m internal diameter beneath the River Thames in Essex for National Grid’s Grain to Tilbury project, delivered by the Ferrovial BEMO joint venture. The drive will pass through variable Thames estuary ground conditions between 35m‑deep launch and reception shafts of 15m and 12m diameter, with tunnelling continuing into 2026 and overall scheme completion targeted for 2029. The new tunnel will replace the 1969 Thames Cable Tunnel and carry new high‑voltage circuits between Grain and Tilbury substations.

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 7 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 6 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

    AllGeotechnicalInfrastructureHazardsEnvironmental