    HS2 Wendover precast green tunnels: sequencing lessons for project engineers

    January 21, 2026|

    Reviewed by Joe Ashwell

    HS2 Wendover precast green tunnels: sequencing lessons for project engineers

    First reported on New Civil Engineer

    30 Second Briefing

    Construction of three cut-and-cover precast “green tunnels” on HS2’s central section at Wendover is being sequenced so delivery teams can copy and refine methods from earlier drives, cutting programme risk and improving safety. Standardised precast portal units and repeatable temporary works details are being reused across the tunnels, allowing faster installation cycles, tighter quality control on waterproofing and backfill, and more predictable ground-structure interaction. Lessons on logistics, lifting operations and working within narrow rural corridors are being transferred between sites to reduce plant clashes and temporary land-take.

    Technical Brief

    • Approach provides a template for multi-site precast tunnel delivery where sequential learning reduces cumulative safety risk.

    Our Take

    HS2’s Wendover green tunnel work sits alongside the recently completed 16 km Chiltern tunnel in our coverage, signalling that the project is now shifting from heavy excavation to more standardised, repeatable civil works where lessons learned can materially cut programme risk.

    With HS2 Ltd appearing across multiple recent UK pieces in our database, the Wendover precast approach is likely to be scrutinised as a template for other HS2 surface structures, especially where community impact and safety performance are politically sensitive.

    The involvement of precast specialists on HS2 elsewhere (for example Banagher Precast Concrete in graphene‑reinforced trials) suggests that process refinements at Wendover could feed into a broader HS2 supply‑chain push towards factory‑controlled quality and reduced on‑site safety exposure across the route.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
    Infrastructure
    in 9 months

    Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

    A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams
    Infrastructure
    in 8 months

    Hudson Tunnel funding deadline: schedule and risk takeaways for project teams

    Federal funding for New York’s US$16bn Hudson Tunnel Project has been frozen, forcing the Gateway Development Commission to suspend works from 6 February after spending over US$1bn and employing about 1,000 site workers. A Manhattan federal judge has issued a temporary restraining order, giving the administration until 5 p.m. on 12 February to restore reimbursements or appeal, while contractors warn that demobilisation, resequencing and remobilisation will add cost and delay. Sites are now in “safe-pause” mode, with dewatering, ground support and environmental monitoring maintained, and assembly of two Herrenknecht TBMs in New Jersey likely to slip beyond the planned spring 2026 launch without funding certainty.

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers
    Infrastructure
    in 5 months

    Implenia/Marti JV MehrSpur Zurich–Winterthur: design and risk notes for engineers

    Swiss Federal Railways has awarded an Implenia/Marti 50:50 joint venture five of six MehrSpur Zurich–Winterthur lots worth just under CHF 1.7 billion, including the 8.3 km Brüttener tunnel (Lot 240) with twin 10 m diameter single-track tubes and a 1 km spur to Zurich Airport. TBM excavation will start in August 2029, with a roughly ten-year construction phase using BIM for planning and execution and extensive special foundations, earthworks and embankments. Additional works cover full redevelopment of Dietlikon station, about 6 km of new track across Dietlikon and Wallisellen sections, multiple underpasses, bridges and the Neumühle railway bridge and Storchen underpass near Winterthur.

    Related Industries & Products

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    QCDB-io

    Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.