    Eldorado Gold’s Skouries capex rise and 18% guidance cut: key points for mine planners

    October 30, 2026|

    Reviewed by Tom Sullivan

    Eldorado Gold’s Skouries capex rise and 18% guidance cut: key points for mine planners

    First reported on MINING.com

    30 Second Briefing

    Eldorado Gold shares fell 7.9% to C$44.44 after it cut 2026 gold guidance 18% to 425,000–475,000 oz. and disclosed a US$160 million underlying capital increase at the Skouries copper-gold project, taking total project capital to about US$1.43 billion. Skouries’ 2026 output outlook was slashed to 10,000–35,000 oz. from 60,000–100,000 oz. as commissioning lengthens, with only two of six tailings filter presses currently operating and temporary generator use adding to costs before grid connection. All-in sustaining costs at existing mines rose 16% at the midpoint to US$1,975–US$2,125/oz., while McIlvenna Bay capex edged up 2.4% to US$975 million, extending cash burn into late 2026.

    Technical Brief

    • Only two of six Skouries tailings filter presses are running; four more due online in November.
    • Temporary power at Skouries relied on generators now removed after grid connection, inflating pre-production operating costs.
    • Total Skouries project capital now US$1.43 billion, with a further US$30 million contingent on start-up timing.
    • Underlying Skouries capital increase is assessed at US$160 million, about 10% above previous estimates.
    • Accelerated Skouries operational capital has risen to US$390 million, up US$130 million from earlier plans.
    • Existing mine guidance cuts are driven by lower output at Kisladag and Olympias, partially offset by Lamaque.
    • Kisladag’s ~300‑day heap leach cycle delays realisation of higher grades now being stacked until late 2027.
    • Olympias’ expansion works are constraining fourth‑quarter plant throughput, reducing short‑term gold output despite longer‑term capacity aims.
    • McIlvenna Bay capex has been revised to US$975 million, excluding all spend incurred before June 2024.
    • Free cash flow excluding Skouries and McIlvenna Bay is positive US$98.3 million, versus a group deficit of US$191.1 million.

    Our Take

    The 72% reduction in expected gold output from Skouries comes despite recent milestones such as permanent grid connection and first concentrate production in September 2026, signalling that the main risk now is in ramp-up performance and plant reliability rather than basic project delivery.

    Skouries’ designation as a strategic project under the EU Critical Raw Materials Act means that even with a 10% underlying capital increase, the gold-copper asset in Greece is likely to retain strong political and permitting backing, which can cushion schedule slippage but not cost or guidance credibility with investors.

    With existing operations’ AISC guidance up 16% and Skouries/McIlvenna Bay driving a US$191.1 million free cash flow deficit, Eldorado Gold’s portfolio now resembles other copper-gold names in our database that are effectively funding multi-asset growth (Canada, Greece, Turkey) out of balance sheet rather than operating cash, increasing sensitivity to further capex creep.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Critical One–SICC antimony offtake: project finance and processing lens for engineers
    Mining
    about 1 hour ago

    Critical One–SICC antimony offtake: project finance and processing lens for engineers

    Critical One Energy has signed a binding MOU with Solar International Core Canada for C$25 million in equity, a construction financing facility of up to C$400 million and exclusive offtake rights for up to 150 million lb of antimony from the Howells Lake antimony-gold project in Ontario. The deal includes C$15 million at C$1.20 per share— a 48% premium to the prior C$0.81 close—giving SICC a 12% fully diluted stake and one board seat, plus a C$10 million carried equity interest for Critical One in an Ontario antimony processing plant led by Northlink Development Group. Located 120 km west of the Ring of Fire access corridor on Eabametoong First Nation homelands, Howells Lake is described as Canada’s largest undeveloped antimony deposit, with current work focused on airborne geophysics and verification of historic antimony-gold zones across the 26 km property.

    Morton Salt Ohio mine water breach: geotechnical failure lessons for engineers
    Mining
    about 1 hour ago

    Morton Salt Ohio mine water breach: geotechnical failure lessons for engineers

    Morton Salt has halted underground mining at its Fairport, Ohio rock salt operation after detecting a “significant inflow of water” on 22 October, triggering an immediate evacuation, shutdown of all underground activities and regulatory notifications. Surface work at the shaft complex is now “severely limited”, with the company declaring force majeure to customers and vendors while independent experts assess the source, extent and geotechnical implications of the water ingress. Local media report dozens of layoffs and say the future of mining at the site remains uncertain.

    Rio Tinto’s $1.4bn Argentina lithium hub: capacity, process routes and risks for mine planners
    Mining
    about 1 hour ago

    Rio Tinto’s $1.4bn Argentina lithium hub: capacity, process routes and risks for mine planners

    Rio Tinto has commissioned its $530 million Fénix 1B expansion and $374 million Sal de Vida lithium carbonate plant in Catamarca, delivering first production in Q2 2026 and adding 25,000 tonnes/year of lithium carbonate equivalent (LCE) capacity. The projects, part of an integrated hub on the Salar del Hombre Muerto with a 19‑million‑tonne LCE resource, lift Rio’s nominal Argentine capacity (including Olaroz) to about 100,000 tonnes/year and combine direct lithium extraction at Fénix with evaporation ponds at Sal de Vida. Further Fénix expansions, including the proposed Fénix II plant, could require around $1 billion and are being lined up for Argentina’s 30‑year RIGI incentive regime.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental