Thames tunnel job finishes early: schedule and grid capacity takeaways for engineers
Reviewed by Joe Ashwell

First reported on The Construction Index
30 Second Briefing
Boring of National Grid’s new Thames cable tunnel for the Great Grid Upgrade has finished 49 days ahead of schedule, using a Herrenknecht tunnel boring machine driven by the Ferrovial Bemo joint venture. Early completion on this river crossing reduces programme risk for subsequent cable installation and commissioning, a critical path activity for reinforcing London’s high‑voltage transmission capacity.
Technical Brief
- TBM drive under a tidal river implies strict control of face pressure and settlement above.
- Under-river alignment likely chosen to avoid congested urban corridors and deep existing utilities.
- Cable tunnel configuration will allow future high-voltage circuits without repeated surface disruption.
- Early handover of the civil tunnel section de-risks interface clashes with specialist cable contractors.
- Programme float gained here can buffer later outages needed for grid connection works.
- Similar urban river-crossing cable tunnels increasingly favour mechanised drives over immersed tubes or HDD.
Our Take
The 49‑day schedule gain on this Thames section of National Grid’s Great Grid Upgrade contrasts with several other UK power tunnel items in our database that report slippage at river crossings, suggesting the Ferrovial Bemo JV/Herrenknecht delivery model is performing at the favourable end of current benchmarks.
Earlier coverage of the Grain–Tilbury TBM and Herrenknecht’s ‘Verena’ VSM shaft sinking shows National Grid standardising on paired mechanised shaft and Mixshield solutions for sub‑river cable routes, which is likely to de‑risk future crossings in the wider Great Grid Upgrade portfolio.
Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.
Related Articles
Related Industries & Products
Tunnelling
Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.
Construction
Quality control software for construction companies with material testing, batch tracking, and compliance management.
CMRR-io
Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.
HYDROGEO-io
Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.
GEODB-io
Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.