Geomechanics.io

  • Free Tools
Sign UpLog In
Projects

Second reactor lifted at Hinkley Point C: constructability lessons for engineers

June 1, 2026|

Reviewed by Tom Sullivan

Second reactor lifted at Hinkley Point C: constructability lessons for engineers

First reported on The Construction Index

30 Second Briefing

Sarens’ SGC-250 “Big Carl” land crane, rated at 250,000 tonne-metres, has lifted the 13-metre-long reactor pressure vessel for Hinkley Point C Unit 2 into the reactor building, where the internal polar crane rotated it vertical and set it onto a support ring with just 40mm lateral clearance. Unit 2 construction is reported to be 20–30% faster than Unit 1, with the outer containment, additional structural steelwork and three large heat exchangers already installed at this stage. EDF plans to transfer these build efficiencies directly to the Sizewell C gigawatt-scale project.

Technical Brief

  • Sarens’ SGC-250 deployment for Unit 2 replaces the temporary overhead lifting system used on Unit 1.
  • The second reactor installation followed less than 12 months after lifting the Unit 2 steel dome.
  • EDF reports Unit 2 is progressing 20–30% faster than Unit 1 using the same design and teams.
  • At the equivalent programme stage, Unit 2 already has its outer containment layer completed.
  • Additional structural steelwork is more advanced in Unit 2 than it was for Unit 1 at this point.
  • Three large heat exchangers are already installed in Unit 2, versus none at the same milestone on Unit 1.

Our Take

EDF’s decision to replicate the Hinkley Point C design at Sizewell C, referenced in the recent AtkinsRéalis framework award, means the 20–30% construction speed gains seen on Unit 2 are likely to be treated as a benchmark for schedule optimisation on the Suffolk project.

Sarens’ heavy-lift role at Hinkley Point C sits within a competitive UK crane market where Mammoet is bringing in a 2,500‑tonne LR12500‑1.0 crawler; this signals that future nuclear and large energy schemes in the United Kingdom will have multiple Tier‑1 heavy-lift options for complex reactor and dome placements.

Geotechnical Software for Modern Teams

Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

No credit card required.

  • Save and export unlimited calculations
  • Advanced data visualisation
  • Generate professional PDF reports
  • Cloud storage for all your projects

Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

Related Articles

Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers
Infrastructure
in 6 months

Strabag’s Pfaffensteig Tunnel contract: design and delivery notes for rail engineers

Strabag and Group company Züblin have secured the design-and-build structural works for the ABS Gäubahn Nord/Pfaffensteig Tunnel in south-west Germany, centred on an 11km twin-bore rail tunnel linking Stuttgart Airport station directly to the Gäubahn line towards Switzerland. About 9.8km will be driven by two TBMs, with conventional tunnelling for the A8 motorway undercrossing and airport connection, plus a 240m cut-and-cover section, retaining structures, railway underpasses and a grade-separated crossing. A 3km surface section will be upgraded and partially realigned for 200km/h operation, delivered under an integrated project delivery model with Ed. Züblin, Wayss & Freytag and Strabag AG sharing tunnelling, structural and earthworks packages.

National Grid TBM under the Thames: tunnelling design and risk notes for engineers
Infrastructure
in 6 months

National Grid TBM under the Thames: tunnelling design and risk notes for engineers

A 271.5‑tonne Herrenknecht Mixshield TBM, Caroline, has started driving a 2.2km electricity cable tunnel with a 4m internal diameter beneath the River Thames in Essex for National Grid’s Grain to Tilbury project, delivered by the Ferrovial BEMO joint venture. The drive will pass through variable Thames estuary ground conditions between 35m‑deep launch and reception shafts of 15m and 12m diameter, with tunnelling continuing into 2026 and overall scheme completion targeted for 2029. The new tunnel will replace the 1969 Thames Cable Tunnel and carry new high‑voltage circuits between Grain and Tilbury substations.

Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers
Infrastructure
in 6 months

Panama Canal Mixshield undercrossing: design and tunnelling lessons for engineers

A 13.46m diameter Herrenknecht Mixshield TBM has broken through into the future Balboa station on Panama Metro Line 3 after completing the first-ever TBM undercrossing of the Panama Canal at depths exceeding 60m below sea level. The 5,600kW, 26,616kNm machine, fitted with an accessible cutterhead and more than 4,500 sensors linked via the Herrenknecht.Connected platform, has achieved peak advance of 150 segment rings (about 300m) per month through mixed sandstone, tuff, breccias and basalt. Around 1.5km of the 4.5km twin-track tunnel remains to final breakthrough.

Related Industries & Products

Construction

Quality control software for construction companies with material testing, batch tracking, and compliance management.

Mining

Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

QCDB-io

Comprehensive quality control database for manufacturing, tunnelling, and civil construction with UCS testing, PSD analysis, and grout mix design management.

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    AllGeotechnicalInfrastructureHazardsEnvironmental