    Resouro PEA for Tiros rare earth and titanium: project economics for mine planners

    June 16, 2026|

    Reviewed by Joe Ashwell

    Resouro PEA for Tiros rare earth and titanium: project economics for mine planners

    First reported on MINING.com

    30 Second Briefing

    Resouro Strategic Metals’ PEA for the Tiros rare earths and titanium project in Minas Gerais, Brazil, outlines a 500,000 t/y starter operation producing about 90,000 t/y TiO₂ concentrate and 3,636 t/y TREO over an initial 20-year mine life, with post-tax NPV8 of $714.9 million and IRR of 44.2%. The deposit hosts 1.4 billion tonnes of measured and indicated resources at 12% TiO₂ and 4,000 ppm TREO, with the starter pit targeting less than 1% of this inventory. Near-surface, low-strip mineralisation, conventional processing, and reported recoveries of 68.7% TiO₂ and 67% REE to mixed carbonate underpin the staged development strategy.

    Technical Brief

    • Measured resources total 367 Mt at 12% TiO₂; indicated resources add a further 1 Bt at 12% TiO₂.
    • Combined measured and indicated inventory of 1.4 Bt at 4,000 ppm TREO underpins very long mine-life optionality.
    • Starter pit exploits near-surface, low-strip mineralisation, implying shallow free-dig or short-haul truck–shovel mining.
    • Dual revenue from TiO₂ concentrate and mixed rare earth carbonate reduces single-commodity price risk in cash-flow modelling.
    • Reported TiO₂ overall recovery of 68.7% and 67% REE to MREC assume conventional beneficiation and hydromet flowsheets.

    Our Take

    With a 1.4Bt measured and indicated resource at 12% TiO₂ and only a sub‑1% slice targeted for the 20‑year starter operation, Tiros in Minas Gerais looks more like a multi‑decade district play than a single‑mine plan, which could materially extend life or support staged expansions if infrastructure and permitting in Brazil keep pace.

    The 68.7% TiO₂ and 67% rare earth recovery to mixed rare earth carbonate place Tiros toward the upper end of recovery assumptions seen in our rare earth and titanium project coverage, which, if confirmed at pilot scale, would help the project compete with hard‑rock peers on operating cost despite being in a Latin American rather than Chinese or Australian jurisdiction.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    South32’s 61% Sierra Gorda reserve lift: life-of-mine and plant planning notes
    Mining
    about 6 hours ago

    South32’s 61% Sierra Gorda reserve lift: life-of-mine and plant planning notes

    South32 has lifted the Sierra Gorda ore reserve in Chile by 61% to 1.1 billion tonnes at 0.39% total copper, 0.016% molybdenum and 0.06 g/t gold (0.46% CuEq), extending reserve life by about five years to 2045 after 85,000 metres of infill drilling from 200 holes. The updated MRE now stands at 1.87 billion tonnes at 0.37% copper (0.44% CuEq), with the orebody remaining open at depth and additional potential at the Catabela Northeast target. A fourth grinding line, approved in July, is expected to lift copper output by roughly 30% from 2031, reinforcing long-term concentrator planning and infrastructure requirements.

    Agnico’s C$57M Radisson stake: O’Brien gold mine access and PEA lens for engineers
    Mining
    about 6 hours ago

    Agnico’s C$57M Radisson stake: O’Brien gold mine access and PEA lens for engineers

    Agnico Eagle Mines is investing C$57.2 million in Radisson Mining Resources for a 10.5%–14.9% stake to advance underground access and infrastructure at the historic O’Brien gold mine in Quebec’s Bousquet-Cadillac camp along the Larder Lake-Cadillac Break. Funding will support an access ramp, underground workings, surface facilities and water management, complementing Radisson’s fully funded 140,000-metre surface drilling and a planned 11-year underground operation with toll milling at IAMGOLD’s Doyon plant. A July 2025 PEA at US$3,300/oz gold pegs O’Brien’s after-tax NPV5 at C$871 million with a 74% IRR, underpinned by recent intercepts such as 5.1 m at 316.31 g/t from 823 m.

    Top of Mine: Costa’s AI-through-mining thesis and what it means for project teams
    Mining
    about 6 hours ago

    Top of Mine: Costa’s AI-through-mining thesis and what it means for project teams

    Otavio (Tavi) Costa, founder and CEO of Azuria Capital, argues that mining equities are currently the cheapest way to gain AI exposure, as sovereign funds and governments re-rate the sector and mid-tier producers move to secure “strategic reserves” by acquiring high-quality junior assets. He links this to a macro backdrop where global debt has returned to World War II levels but only about 3% of the US Treasury market is now backed by gold, versus roughly 50% then. With spot gold at $4,673.20/oz, Costa expects reserve depletion, weak discoveries and a “global monetary race towards gold” to drive prices substantially higher.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental