    Newmont’s Red Chris $4.8B block cave: capex, schedule and design notes for engineers

    October 24, 2026|

    Reviewed by Joe Ashwell

    Newmont’s Red Chris $4.8B block cave: capex, schedule and design notes for engineers

    First reported on MINING.com

    30 Second Briefing

    Newmont has priced the Red Chris block cave expansion in British Columbia at $4.2–$4.8 billion (including contingency and assuming a C$500 million federal contribution), targeting first underground production in 2033 and average output of 275,000–325,000 oz. gold and 65,000–85,000 tonnes copper from 2035–2040. Engineering is at least 60% complete, the cave has been reoriented to avoid major fault intersections, and initial development covers two mining blocks over 13 years with potential mine life up to 70 years. Development capex will rise about $500 million next year to $1.9 billion, with Red Chris accounting for roughly $250 million, funded from internal cash flow.

    Technical Brief

    • Newmont’s capex estimate of $4.2–$4.8 billion explicitly excludes open-pit to underground transition costs.
    • Scope change from Newcrest’s 2021 PFS: three blocks over 31 years reduced to two blocks over 13 years.
    • Initial underground phase is planned to deliver 3 Moz gold and >850,000 tonnes copper before any East Ridge add-ons.
    • Federal C$500 million support is assumed but still subject to negotiation on terms and structure.
    • B.C. permits were issued via a consent-based process with the Tahltan Nation, de-risking Indigenous approvals.
    • Ottawa’s Major Projects Office is coordinating Red Chris approvals and financing, one of only five such projects.
    • Red Chris will drive about $250 million of the ~$500 million year-on-year development capex increase, partly offset by lower Yanacocha reclamation spend.

    Our Take

    With Red Chris contributing only about 2% of Newmont’s estimated NAV but demanding up to US$4.8 billion in capex, the project effectively represents a long-dated copper-gold option that could be more about strategic copper exposure in British Columbia than near-term value accretion at the corporate level.

    The step-up of roughly US$500 million in development spend next year, half of it tied to Red Chris, comes as Newmont is also managing large commitments at Tanami and Lihir; in our database, this kind of multi-asset capital load has often preceded portfolio pruning or JV rationalisations at other majors to protect balance sheets.

    Commercial production at Red Chris only around 2033 means the mine will not help Newmont reach the 6-million-ounce annual gold level that BMO is watching for by 2027, so any move towards that target will have to come from debottlenecking or brownfield expansions at existing operations such as Boddington, Peñasquito or Cerro Negro rather than this Canadian build-out.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Bannerman’s US$353M Etango uranium mine: project funding and delivery notes for engineers
    Mining
    about 2 hours ago

    Bannerman’s US$353M Etango uranium mine: project funding and delivery notes for engineers

    Bannerman Energy and CNNC Overseas have approved full-scale construction of the Etango open-pit, heap-leach uranium mine in Namibia’s Erongo region, a US$353 million development designed to process 8 million tonnes of ore per year and produce about 3.5 million lb U₃O₈ annually from 2028. The project is fully funded without project debt, with CNNC investing US$320.4 million and securing offtake for 60% of lifetime production on market-based terms, while Bannerman markets the remaining 40%. Bulk earthworks are 99% complete, early works have already consumed US$64 million, and the first stage of the permanent water pipeline is about 90% finished, signalling limited geotechnical and infrastructure risk heading into main construction.

    Moon River’s Davidson NPV jumps to $879M: economics and design notes for mine planners
    Mining
    about 2 hours ago

    Moon River’s Davidson NPV jumps to $879M: economics and design notes for mine planners

    Moon River Moly’s updated PEA lifts the Davidson underground molybdenum-copper-tungsten project’s after-tax NPV to C$1.23 billion at an 8% discount rate and cuts payback to 1.5 years, driven by a switch from gravity separation to tungsten flotation and revised capex/opex. The 10,000 t/d, 20-year operation now targets average annual output of 13.27 million lb molybdenum, 1.5 million lb copper and 1.51 million lb WO₃, with all-in sustaining costs of $4.36/lb Mo net of by-products. Tungsten resources are upgraded to 80.8 million tonnes measured and indicated, and the mine plan includes battery-electric equipment, paste backfill and dry-stack tailings.

    Nicaragua mining bridgehead: project scale and security lens for engineers
    Mining
    about 2 hours ago

    Nicaragua mining bridgehead: project scale and security lens for engineers

    Chinese state-aligned miners have secured concessions over more than one million hectares in Nicaragua—around 8.5% of national territory—targeting high-grade epithermal gold systems such as the 50 km La India district, valued at an estimated $1.4 billion NPV. The gold endowment, with co-metals including antimony, tellurium and silver for infrared sensors and munition fuses, provides Managua with sanctions-resistant “war liquidity” while deepening Beijing’s resource portfolio. With Ortega’s removal of competitive elections, 30-year, state-backed concessions near the Panama Canal and 1,000 miles from the US border raise explicit anti-access/area-denial concerns for Western defence supply chains.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental