    Minnova’s C$76M PL gold mine restart: economics and strip risks for engineers

    First reported on MINING.com

    30 Second Briefing

    Minnova plans a C$76.2 million restart of the brownfield PL gold mine near Sherridon, Manitoba, targeting 62,200 oz per year over 10 years from a high‑grade open pit feeding an existing 1,000 t/d plant, which is slated to double to 2,000 t/d in year two. The September resource stands at 3.76 million measured and indicated tonnes at 4.98 g/t Au (601,158 oz) plus 1.67 million inferred tonnes at 3.78 g/t (202,810 oz), with open pits carrying a high 21:1 waste‑to‑ore strip ratio. At US$3,000/oz gold, the PEA projects an after‑tax NPV5 of US$180.6 million, 111% IRR, eight‑month payback and all‑in sustaining costs of US$2,288/oz, but value falls sharply at lower prices, underlining cost and strip sensitivity.

    Technical Brief

    • Open-pit design carries an extreme 21:1 waste-to-ore strip ratio, driving haulage and unit cost risk.
    • New plan pivots from the 2017 feasibility’s underground-focused, five-year schedule to a longer open-pit–led mine life.
    • Historical 2017 study projected 46,500 oz/y at US$942/oz AISC, assuming US$1,250/oz gold and excluding inferred resources.
    • September resource drilling campaign totalled 13,500 m in 131 holes, aimed at both expansion and confidence upgrade.
    • Open-pit component currently defined as 1.58 Mt measured and indicated at 5.28 g/t Au (268,091 oz).
    • Existing environmental licence only covers underground mining, so Minnova must secure amendments for open pits and new declines.
    • Site, formerly Puffy Lake, previously operated December 1987–March 1989, implying legacy workings and potential geotechnical/rehab constraints.
    • Economic sensitivity is extreme: a 20% gold price drop to US$2,400/oz reduces after-tax NPV5 to only US$5 million.

    Our Take

    With a C$19 million market valuation against an after-tax NPV of about $180.6 million at $3,000/oz gold, Minnova’s PL gold mine in Manitoba screens as a high-leverage, high-risk equity in our gold project coverage, which may appeal more to specialist funds than generalist institutions.

    The 21:1 waste-to-ore strip ratio at the PL open pits is at the upper end of what operators in our database typically tolerate for small Canadian gold projects, suggesting that any cost inflation or productivity underperformance could quickly erode margins unless the underground component or grade control outperforms expectations.

    The move from a 5-year mine life in the 2017 feasibility study to a 10-year production period in the latest assessment puts PL more in line with mid-tier Manitoba gold assets in our database, which can improve financing prospects but also raises the bar for demonstrating long-term geotechnical and permitting robustness near Sherridon.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 1 hour ago

    Caterpillar Resource Industries leadership shift: fleet and autonomy cues for miners

    Caterpillar has confirmed that Denise Johnson, Group President of Resource Industries since 2016 and a key figure in expanding autonomous haulage and large mining truck platforms, will retire on 1 February 2027. Derrick York, currently President of Solar Turbines and a Caterpillar Senior Vice President overseeing industrial gas turbines and compressor sets, will become Group President of Resource Industries on 1 November 2026, with Johnson shifting to an advisory role. The handover timetable gives miners nearly a year of overlap to align major fleet, autonomy and support contracts with the incoming leadership.

    Anglo American copper scarcity and tech tie-ups: key takeaways for mine planners
    Mining
    about 1 hour ago

    Anglo American copper scarcity and tech tie-ups: key takeaways for mine planners

    Tech companies are in talks to buy equity in Anglo American to secure long-term copper and other data centre metals, as Comex copper trades near $6.52/lb and LME cash copper recently hit a record $14,822/t. Anglo’s planned merger with Teck Resources would create a roughly $90 billion group producing about 1.2 million tonnes of copper per year, controlling around 5% of global supply, but is still awaiting Chinese antitrust clearance tied to concentrate flows to local smelters. Wanblad also warned Anglo may close its Brazilian nickel operations at Codemin and Barro Alto if the EU blocks the $500 million sale to MMG despite proposed long-term European ferronickel supply commitments.

    Mining
    about 1 hour ago

    Wolong Electric & AEAUTO mining truck conversions: cost and retrofit notes for fleets

    Wolong Electric and AEAUTO have entered China’s fast-growing diesel-to-electric mining truck conversion market, joining established players such as HATL (Fujian Hongda Contemporary Amperex Technology Co Ltd) and Huigong Group’s Xingdong Lithium Battery Technology Co Ltd (XDLE). The move expands the supply base for high-capacity lithium battery systems and electric drivetrains tailored to large haul trucks operating in Chinese open pits. For mine operators, increased competition in conversion packages should sharpen pricing and accelerate retrofits of existing diesel fleets rather than full replacement purchases.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental