Geomechanics.io

  • Free Tools
Sign UpLog In
Built byBoxcut Studio

Geomechanics.io

Geomechanics, Streamlined.

© 2026 Geomechanics.io. All rights reserved.

Geomechanics.io

CMRR-ioGEODB-ioHYDROGEO-ioQCDB-ioFree Tools & CalculatorsBlogLatest Industry News

Industries

MiningConstructionTunnelling

Company

Terms of UsePrivacy PolicyLinkedIn
    Projects

    Ivanhoe’s Platreef expansion: throughput, hoisting and cost lens for mine planners

    April 24, 2026|

    Reviewed by Joe Ashwell

    Ivanhoe’s Platreef expansion: throughput, hoisting and cost lens for mine planners

    First reported on MINING.com

    30 Second Briefing

    Ivanhoe Mines’ Platreef project in Limpopo has completed construction of the 4‑Mtpa Shaft #3, broken ground on a 3.3‑Mtpa Phase 2 concentrator and started widening Shaft #2, keeping its Phase 2 expansion on schedule for end‑2027. Hoisting capacity is set to rise five‑fold to about 5 Mtpa, lifting output from roughly 100,000 oz to over 450,000 oz of PGMs plus gold, with a projected Phase 2 life‑of‑mine cash cost of $599/oz net of byproduct credits. A future Phase 3 could take throughput to 10.7 Mtpa and extend mine life by 29 years.

    Technical Brief

    • Shaft #3 is designed for 4 Mtpa hoisting, relieving current ore and waste constraints on Shaft #1.
    • Widening of Shaft #2 has commenced; once complete it will be Africa’s largest hoisting shaft.
    • Shaft #2 is scheduled to hoist labour and materials by end‑2028, and ore by end‑2029.
    • Phase 2 concentrator earthworks are underway, targeting completion of the 3.3‑Mtpa plant by end‑next‑year.
    • Ownership structure includes 26% held by a B‑BBEE group and 10% by the JOGMEC‑ITOCHU consortium.
    • The orebody averages 26 m of continuous, flat‑lying mineralisation, around 25 times thicker than incumbents.
    • Thick, flat geometry enables high mechanisation, directly supporting lower unit mining costs and improved safety conditions.
    • Preliminary economic assessment forecasts >1 Moz PGMs+Au per year plus ~22 kt Ni and 13 kt Cu after all expansions.

    Our Take

    Ivanhoe Mines features repeatedly in our recent coverage, from the Platreef Phase 2 concentrator HPGR contract with Weir (March 2026) to revised Kamoa-Kakula copper guidance (April 2026), signalling that Platreef’s platinum-group, nickel and copper output is being advanced in parallel with a broader portfolio reset.

    With a 35-year mine life post-Phase 2 and a further 29 years contemplated in Phase 3, Platreef in South Africa stands out in our database as one of the longer-life polymetallic assets, which typically underpins more aggressive downstream and offtake negotiations for platinum, palladium, rhodium and nickel than shorter-life PGM mines.

    The 26% B-BBEE and 10% JOGMEC-ITOCHU ownership stakes at Platreef give both domestic empowerment interests and Japanese buyers structural leverage over a low-cost, multi-decade PGM–nickel–copper supply source, which is strategically relevant given Ivanhoe’s concurrent critical-minerals positioning in projects like Kipushi under US-linked initiatives.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Minnova’s C$76M PL gold mine restart: economics and strip risks for engineers
    Mining
    about 7 hours ago

    Minnova’s C$76M PL gold mine restart: economics and strip risks for engineers

    Minnova plans a C$76.2 million restart of the brownfield PL gold mine near Sherridon, Manitoba, targeting 62,200 oz per year over 10 years from a high‑grade open pit feeding an existing 1,000 t/d plant, which is slated to double to 2,000 t/d in year two. The September resource stands at 3.76 million measured and indicated tonnes at 4.98 g/t Au (601,158 oz) plus 1.67 million inferred tonnes at 3.78 g/t (202,810 oz), with open pits carrying a high 21:1 waste‑to‑ore strip ratio. At US$3,000/oz gold, the PEA projects an after‑tax NPV5 of US$180.6 million, 111% IRR, eight‑month payback and all‑in sustaining costs of US$2,288/oz, but value falls sharply at lower prices, underlining cost and strip sensitivity.

    Mining
    about 7 hours ago

    Caterpillar Resource Industries leadership shift: fleet and autonomy cues for miners

    Caterpillar has confirmed that Denise Johnson, Group President of Resource Industries since 2016 and a key figure in expanding autonomous haulage and large mining truck platforms, will retire on 1 February 2027. Derrick York, currently President of Solar Turbines and a Caterpillar Senior Vice President overseeing industrial gas turbines and compressor sets, will become Group President of Resource Industries on 1 November 2026, with Johnson shifting to an advisory role. The handover timetable gives miners nearly a year of overlap to align major fleet, autonomy and support contracts with the incoming leadership.

    Anglo American copper scarcity and tech tie-ups: key takeaways for mine planners
    Mining
    about 7 hours ago

    Anglo American copper scarcity and tech tie-ups: key takeaways for mine planners

    Tech companies are in talks to buy equity in Anglo American to secure long-term copper and other data centre metals, as Comex copper trades near $6.52/lb and LME cash copper recently hit a record $14,822/t. Anglo’s planned merger with Teck Resources would create a roughly $90 billion group producing about 1.2 million tonnes of copper per year, controlling around 5% of global supply, but is still awaiting Chinese antitrust clearance tied to concentrate flows to local smelters. Wanblad also warned Anglo may close its Brazilian nickel operations at Codemin and Barro Alto if the EU blocks the $500 million sale to MMG despite proposed long-term European ferronickel supply commitments.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Construction

    Quality control software for construction companies with material testing, batch tracking, and compliance management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental