    Hormuz Strait closure and sulphur shock: implications for copper leach projects

    April 13, 2026|

    Reviewed by Joe Ashwell

    Hormuz Strait closure and sulphur shock: implications for copper leach projects

    First reported on MINING.com

    30 Second Briefing

    A prolonged closure of the Strait of Hormuz, which normally carries over 40% of global sulphur exports, combined with China’s 2.7‑million‑tonne annual sulphuric acid export ban from 1 May, is driving sulphuric acid prices above $500/t and threatening about 20% of global copper supply that depends on acid leaching. Ivanhoe Mines’ Kamoa‑Kakula complex, hosting Africa’s largest copper smelter, produced 117,871 tonnes of high‑strength sulphuric acid and 71,417 tonnes of copper anode in Q1, giving it a cost and supply advantage as a net acid seller. Despite this, Ivanhoe has cut 2026 copper anode guidance to 290,000–330,000 tonnes and is implementing contingency measures, including advanced diesel purchases, to sustain operations during the US‑led war on Iran.

    Technical Brief

    • Closure of the Strait of Hormuz removes about 50% of global seaborne sulphur supply, tightening acid feedstock.
    • China’s 1 May export ban targets sulphuric acid by-product from domestic copper and zinc smelters.
    • Asia’s largest economy had been exporting ~2.7 Mt/y of sulphuric acid, with Chile as top destination.
    • Phosphate fertiliser production consumes 54% of global sulphuric acid demand, versus 10% for metals and mining.
    • Within metals and mining, copper smelting accounts for 62 Mt of an 89 Mt sulphuric acid consumption base.
    • Realised sulphuric acid prices have already exceeded US$500/t under current supply constraints.
    • Kamoa-Kakula’s smelter produced 63,671 t copper in anode plus 117,871 t high-strength sulphuric acid in Q1.
    • Additional 7,746 t of copper in blister were produced at the Lualaba smelter in Kolwezi during the quarter.
    • Kamoa-Kakula’s resource stands at ~1.3 Bt grading 2.65% Cu, containing ~34 Mt copper metal.
    • Ivanhoe’s contingency planning for the US-led war on Iran includes forward purchasing of diesel for operations continuity.

    Our Take

    Ivanhoe Mines has been a recurring name in our recent coverage, from Kamoa-Kakula guidance cuts in early April 2026 to US-facing offtake discussions for Kipushi concentrates, so any disruption to sulphur or sulphuric acid flows via the Middle East would compound an already complex logistics and marketing picture for the company’s African assets.

    In our database of 1212 Mining stories, copper consistently appears alongside critical-mineral themes and US strategic stockpiling moves (e.g. the February 2026 US$12 billion stockpile piece), suggesting that any shock to Middle East sulphur exports could quickly be framed not just as a cost issue but as a supply-security concern for Western copper and fertiliser buyers.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 4 hours ago

    Kathleen Valley expansion: early works and procurement lessons for mine planners

    Early works and long‑lead procurement have started for Liontown Limited’s planned expansion of the Kathleen Valley Lithium Operation in Western Australia, ahead of a formal Final Investment Decision targeted for the end of Q1 FY2027. The programme covers critical items and packages whose fabrication and delivery times could otherwise delay ramp‑up of the underground mine and processing plant. Early commitment to these components signals a push to lock in key OEM capacity and manage schedule risk in a tight lithium project pipeline.

    Metals Australia’s $2.05B Baie‑Comeau graphite refinery: project and IRR lens for engineers
    Mining
    about 5 hours ago

    Metals Australia’s $2.05B Baie‑Comeau graphite refinery: project and IRR lens for engineers

    Metals Australia plans a C$2.05 billion high‑purity graphite refinery near Baie‑Comeau, Quebec, designed to process 75,000 tonnes per year of flake graphite concentrate into 51,000 tonnes of battery‑grade products over a 25‑year life, with a projected 25.6% internal rate of return and 227 permanent jobs. Feedstock will come from its Fermont project averaging 10.2% graphite, about 2.4 times higher grade than publicly reported for Nouveau Monde Graphite, and the site leverages rail‑ferry links plus a deep‑water port. The company will bypass a traditional PFS, moving directly to final feasibility while running parallel community and Indigenous engagement to meet Canada’s 2040 graphite mine and refinery targets.

    Ur-Energy’s Shirley Basin uranium start-up: ISR project metrics for mine planners
    Mining
    about 5 hours ago

    Ur-Energy’s Shirley Basin uranium start-up: ISR project metrics for mine planners

    Ur-Energy has begun in situ recovery uranium production from Mine Unit 1 at its Shirley Basin project in Wyoming, capturing uranium-bearing solution following completion of wellfield installation, processing circuits and permitting. The project has licensed annual wellfield and toll-processing capacity of up to 2.0 million lb U₃O₈ equivalent, with 9.1 million lb U₃O₈ in Measured and Indicated resources at an average 0.22% eU₃O₈ and an anticipated nine-year mine life across three shallow units. Uranium is loaded onto ion exchange resin on site and is expected to be trucked to the Lost Creek plant for final processing, drying and packaging from this summer, pending a further regulatory inspection.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalInfrastructureHazardsEnvironmental