Forrestania’s Edna May gold restart: ramp-up schedule and plant notes for engineers
Reviewed by Tom Sullivan

First reported on Australian Mining
30 Second Briefing
Forrestania Resources is targeting mid-December for first gold production from the restarted Edna May processing facility in Western Australia, as refurbishment and production-readiness works accelerate. Mill liner shipments are en route, with delivery to site scheduled for the final week of November to allow reline and commissioning of the grinding circuit. Completion of the first cell of the processing circuit is a key milestone, signalling imminent wet commissioning and a rapid ramp-up path for nearby open-pit and stockpile feed.
Technical Brief
- Refurbishment scope centres on bringing the existing Edna May CIL plant back to operational readiness.
- Forrestania is leveraging brownfield processing infrastructure rather than constructing a new greenfield plant.
- Restart strategy depends on synchronising mill reline completion with downstream circuit wet commissioning.
- Early completion of the first processing cell allows staged commissioning, limiting whole-of-plant downtime risk.
- Logistics risk is concentrated in timely delivery of mill liners to a remote Western Australian site.
- Using existing open-pit ore and stockpiles reduces pre-strip and mine development lead times for feed.
- Brownfield restart model at Edna May mirrors recent WA gold restarts prioritising capex-light, schedule-compressed refurbishments.
Our Take
Our database shows Forrestania Resources rapidly building a Western Australia gold hub around Edna May, with recent pieces on the Tampia resource and Johnson Range reserve both flagged as feed sources for the same processing infrastructure.
The September item on Forrestania securing rights to process up to two million tonnes of third‑party ore suggests the Edna May processing facility is being positioned as a toll‑treating and regional consolidation asset rather than a single‑mine plant.
Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.
Related Articles
Related Industries & Products
Mining
Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.
Construction
Quality control software for construction companies with material testing, batch tracking, and compliance management.
CMRR-io
Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.
HYDROGEO-io
Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.
GEODB-io
Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.